India Wind 100 GW Target: Government Factsheet Sets 100 GW by 2030 and 156 GW by 2036

India’s wind energy sector is aiming for 100 GW of installed capacity by 2030 and 156 GW by 2036, according to a factsheet titled “Global Wind Day 2026: Charting India’s Path to 100 GW and Beyond”, posted by the Press Information Bureau (PIB) on 14 June 2026. The document, prepared ahead of the Global Wind Day 2026 Conference in Goa on 15 June 2026, says India’s wind resource base provides “a strong foundation” for the India wind 100 GW target. It also lists the capacity, manufacturing and policy measures behind the goal. Figures below are those given in the factsheet, which reports installed capacity as of March 2026.

Where India’s wind capacity stands

Installed wind capacity rose from 21.04 GW in March 2014 to 56.09 GW in March 2026, a 2.66-fold increase, and India ranks 4th in the world in installed wind power capacity. A further 28 GW is under implementation. To reach 100 GW by 2030, the country would need to add roughly 44 GW to the March 2026 base, a figure derived from the two numbers in the factsheet rather than stated in it.

The year 2025-26 set a record. India added 6.05 GW of wind capacity in that financial year, its highest annual addition, against the previous record of 4.15 GW in 2024-25. The factsheet also notes that nearly 45% of wind generation occurs during peak demand hours, which complements solar power and supports grid reliability.

Wind resource potential

The factsheet puts India’s estimated gross wind power potential at 695.5 GW at 120 metres above ground level and 1,163.9 GW at 150 metres. At 150 metres, most of the assessed potential sits in eight states:

Advertisement
  • Rajasthan: 284.2 GW
  • Gujarat: 180.8 GW
  • Maharashtra: 173.9 GW
  • Karnataka: 169.3 GW
  • Andhra Pradesh: 123.3 GW
  • Tamil Nadu: 95.1 GW
  • Madhya Pradesh: 55.4 GW
  • Telangana: 54.7 GW

More than 900 wind-monitoring stations have been installed across the country to map wind resources and identify high-potential sites.

Manufacturing base

Wind turbine manufacturing capacity in India has grown from 10 GW in 2014 to about 24 GW as of March 2026. The sector has reached 70-80% indigenisation across key components, with domestic supply chains for blades, towers, gearboxes and other critical equipment.

Government measures listed in the factsheet

The factsheet groups the government’s wind interventions around wider deployment, offshore development and grid modernisation:

  • Viability Gap Funding (VGF) of Rs 6,853 crore has been approved for 1,000 MW of offshore wind projects, made up of 500 MW each off the coasts of Gujarat and Tamil Nadu.
  • Rs 500 crore was disbursed under the Generation Based Incentive (GBI) scheme during 2025-26.
  • A 500 MW pilot project has been launched under Contracts for Difference (CfD), a mechanism meant to reduce price volatility and give renewable developers revenue certainty.
  • A Task Force was constituted in January 2026 to address regulatory, land, transmission and implementation challenges.
  • A dedicated wind component has been introduced under Renewable Purchase Obligations (RPOs) to ensure sustained demand.
  • Green Energy Open Access Rules have been introduced to help industries buy renewable power directly.
  • Hybrid and Round-the-Clock (RTC) renewable energy projects are being promoted to improve grid efficiency.

Priorities for the next phase

The factsheet lists five priorities for wind energy:

Advertisement
  1. Expanding wind deployment into emerging states such as Madhya Pradesh, Telangana and Odisha.
  2. Launching India’s offshore wind sector through identified leasing areas in Gujarat and Tamil Nadu.
  3. Integrating wind power into RTC renewable energy solutions through storage-linked business models.
  4. Modernising the grid and deploying Artificial Intelligence (AI)-based forecasting tools for renewable energy management.
  5. Strengthening domestic manufacturing across the entire wind energy value chain.

International partnerships

India is also building wind cooperation with the United Kingdom, Denmark and Belgium, with a focus on offshore wind, technology transfer and grid integration. The India-United Kingdom Offshore Wind Taskforce was launched in February 2026 under Vision 2035 and the Fourth India-UK Energy Dialogue, with market design, port infrastructure, supply chains and blended finance as focus areas. At the World Economic Forum 2026, India and Belgium reaffirmed cooperation in offshore wind, research and development, and green taxonomy.

India’s 2019 cooperation agreement with Denmark on offshore wind capacity building was renewed in May 2025.

What it means for India’s clean-energy sector

The factsheet positions wind as more than a stand-alone source of power. Its priorities link wind to storage-linked RTC solutions, hybrid projects and AI-based forecasting. The push into Madhya Pradesh, Telangana and Odisha would broaden a market concentrated in a few states, while offshore VGF and leasing areas open a new segment for developers and equipment makers.

The factsheet is also frank about constraints: realising the opportunity will require faster project execution, stronger transmission infrastructure, improved forecasting and continued policy support. Meeting the 2030 goal will depend on how quickly the 28 GW under implementation is commissioned and whether the 2025-26 pace of additions can be sustained.