The Central Electricity Regulatory Commission (CERC) has adopted a tariff of Rs 4.48 per kWh for 1,050 MW of additional “Greenshoe” capacity under the 1,200 MW firm and dispatchable renewable energy (FDRE) tender of NHPC Limited. In its order dated 19 November 2026 in Petition No. 94/AT/2026, the Commission reduced the allocation of Juniper Green Energy Private Limited under the Greenshoe option from 300 MW to 200 MW. NHPC had asked for adoption of tariff for 1,150 MW.
The NHPC Greenshoe FDRE tariff order covers renewable power projects connected to the inter-state transmission system (ISTS) and coupled with energy storage. The approved capacity is split among Avaada Energy Private Limited (600 MW), Juniper Green Energy Private Limited (200 MW) and ACME Solar Holdings Limited (250 MW), all at Rs 4.48 per kWh.
What NHPC asked for
NHPC, acting as the renewable energy implementing agency, filed the petition under Section 63 of the Electricity Act, 2003, which requires the commission to adopt a tariff determined through transparent bidding under Central Government guidelines. It sought adoption of tariff for 1,150 MW of Greenshoe capacity, allotted through letters of award dated 30 January 2025: 600 MW for Avaada, 300 MW for Juniper Green and 250 MW for ACME Solar. Jevargi Solar Power Private Limited took no additional capacity. NHPC also asked that a trading margin of Rs 0.07 per kWh be recovered from buying utilities, on top of the tariff.
Background of the tender
The tender (2024_NHPC_813414_1) was issued on 28 June 2024 for 1,200 MW of ISTS-connected FDRE capacity to be set up anywhere in India, with a Greenshoe option of up to 1,200 MW more. Bids were invited for a 25-year term in a two-envelope process followed by a reverse auction. Five bids were received, and the e-reverse auction was held on 10 December 2024.
The base allocations were Jevargi Solar Power, 150 MW at Rs 4.48 per kWh; Juniper Green, 200 MW at Rs 4.56 per kWh; Avaada, 600 MW at Rs 4.56 per kWh; and ACME Solar, 250 MW at Rs 4.56 per kWh. CERC adopted this 1,200 MW in its order of 19 June 2025 in Petition No. 87/AT/2025, but not the Greenshoe tariff, as NHPC had neither prayed for it nor argued it then. A review petition (14/RP/2025) was dismissed on 15 January 2026, with liberty to file a fresh petition, which led to the present case.
Under the tender, bidders were asked to take Greenshoe capacity at the lowest tariff found in the auction, Rs 4.48 per kWh, even though three of them had quoted Rs 4.56 per kWh for base capacity.
How the Commission decided
The Commission noted that the Ministry of Power’s guidelines under Section 63 do not expressly provide for, or define, a “Greenshoe Option”. NHPC had included it in the original request for selection document. The Commission observed that allocating additional capacity this way might raise concerns on transparency, consistency and equal treatment of bidders.
It referred to earlier orders (773/AT/2025, 643/AT/2025 and 79/AT/2024) in which it had, ex abundanti cautela, permitted additional capacity under a purported Greenshoe option, and to a Ministry of Power communication dated 28 October 2025. The Commission said it expects implementing agencies not to use the option in future without an express provision in the bidding guidelines. As this is a legacy case, with a request for selection dated 28 June 2024, it adopted the individual tariffs in the interest of regulatory consistency, while restricting Juniper Green’s additional capacity to 200 MW.
Conditions and next steps
Adoption of the tariff is subject to the signing of power sale agreements (PSAs) with distribution licensees. NHPC told the Commission it has approached states and discoms for in-principle consent for the base and Greenshoe capacity, after which it will sign PSAs with discoms and back-to-back power purchase agreements (PPAs) with the generators. Commissioning is to be completed within 24 months from the date of signing of the PPAs.
According to details NHPC filed after the Commission’s record of proceedings dated 24 April 2026, only ACME Solar’s 250 MW is tied up: its PPA was signed on 29 January 2026 and the back-to-back PSA with Punjab State Power Corporation Limited on 27 January 2026. For Avaada and Juniper Green the order shows no PPA or PSA dates. NHPC must place the PPAs and PSAs on record once capacity is tied up, and report if any awarded capacity does not result in them.
On the trading margin, the Commission said that if distribution licensees agree to Rs 0.07 per kWh, it will be deemed to be in line with Regulation 8(1)(d) of the Trading Licence Regulations.
What it means for India’s clean-energy sector
Together with the 1,200 MW base capacity, the 1,050 MW now approved takes the tender to 2,250 MW of FDRE capacity cleared at the regulatory stage, though much still depends on discoms signing PSAs. The order also signals tender design expectations: the Commission wants a Greenshoe provision in the central bidding guidelines before agencies use it again. For developers, it shows that a Greenshoe allocation can be trimmed even after letters of award and an auction, and that tariff adoption does not by itself guarantee offtake.