CERC Holds Ambuja Cements’ 150 MW Rajasthan Captive Solar Plant Eligible for ISTS Charge Waiver

The Central Electricity Regulatory Commission (CERC) has accepted a committee’s recommendation to extend the scheduled commercial operation date (SCOD) of cement maker Ambuja Cements Limited’s 150 MW captive solar plant in Rajasthan to 8 August 2025. The ruling holds the plant eligible for a waiver of inter-state transmission system (ISTS) charges as if it had started operating by 30 June 2025. The plant sits in the 750 MW Phalodi-Pokhran solar park of Essel Saurya Urja Company of Rajasthan Limited (ESUCRL). The order was posted on 20 November 2026.

Key Details of the Order

The Commission decided Petition No. 135/MP/2026, filed by Ambuja Cements against the Central Transmission Utility of India Limited (CTUIL) and ESUCRL. The main points are:

  • Project: a 150 MW solar plant at ESUCRL’s 750 MW solar park at Phalodi-Pokhran, built for captive use across Ambuja Cements’ cement facilities in India.
  • Original SCOD: 30 June 2025.
  • Actual COD: 70 MW on 2 August 2025 and the full 150 MW on 8 August 2025.
  • Cause of delay: late allocation of land and late commissioning and charging of the solar park’s pooling station, which was charged on 8 July 2025.
  • Outcome: SCOD extended to 8 August 2025 and the project held eligible for the waiver under Regulation 13(2)(h) of the CERC Sharing Regulations, 2020.

The order does not state the rupee value of the charges waived, the plant’s cost or its expected generation.

How the Plant Was Delayed

Ambuja Cements told CERC that it installed the full 150 MW in about nine months, from October 2024 to 9 June 2025, against a standard implementation period of 18 months. The Central Electricity Authority approved 100 MW on 20 June 2025 and 50 MW on 22 June 2025. The company applied for first-time charging to the Northern Regional Load Despatch Centre on 28 June 2025.

ESUCRL said the park’s common infrastructure, including the pooling station and evacuation system, was delayed by force majeure events beyond its control. The Northern Regional Load Despatch Centre approved charging of ESUCRL’s main pooling substation on 7 July 2025, and the station was charged the next day. Ambuja Cements told CERC that it achieved COD immediately upon that charging, for 70 MW and then for the remaining 80 MW.

Advertisement

The Committee’s Recommendation

Ambuja Cements applied on 11 November 2025 to the committee that CERC set up under Regulation 13(2)(h) to examine such requests. In its report of 5 January 2026, the committee found that the delay was beyond the developer’s control and was mainly due to solar park infrastructure. It noted that the Ministry of New and Renewable Energy (MNRE) had extended the park’s development timeline in recognition of force majeure-like events. It recommended extending the SCOD to 8 August 2025.

CTUIL said it adopted the committee’s recommendation and would not file a separate reply. CERC had ESUCRL added as a party, reviewed its documents on the park’s delays and accepted the recommendation.

Policy Backdrop

Regulation 13(2)(h) covers wind, solar, wind-solar hybrid and battery storage projects that qualify for an ISTS charge waiver and had an SCOD on or before 30 June 2025. If such a project receives an extension for force majeure, including non-availability of transmission, or for reasons not attributable to it, it keeps the waiver as if it had reached COD on 30 June 2025. Each extension cannot exceed six months at a time, and no more than two extensions are allowed beyond that date.

For projects whose power purchase agreements followed competitive bidding, the regulation says the implementing agency, distribution licensee or MNRE grants the extension. In other cases, such as this captive plant, CERC grants it on the committee’s recommendation.

The Solar Park’s Long Timeline

ESUCRL is a 50:50 joint venture of the Government of Rajasthan and Essel Infra Ltd. MNRE approved the 750 MW park on 14 May 2018, after the District Collector allotted land on 23 March 2018. Under MNRE’s scheme dated 12 December 2014, the park was originally due by 17 June 2017. ESUCRL told CERC that MNRE extended the deadline several times, including to 30 September 2025 by a letter dated 27 June 2025.

Advertisement

The park reached full commercial operation on 31 December 2025. It added 300 MW on 18 June 2021, 150 MW on 1 July 2024, Ambuja Cements’ 150 MW in August 2025 and a final 150 MW on 31 December 2025. The park was therefore completed within the extended timeline, ESUCRL said. An MNRE office memorandum dated 17 September 2025 later extended the timeline for ongoing parks under the scheme to 31 March 2029.

About Ambuja Cements

Ambuja Cements’ investor presentation for the quarter ended 30 September 2026 shows green power capacity of 973 MW and waste heat recovery capacity of 228 MW. In its Q2 FY27 media release, it said it was investing in 1 GW of renewable energy (solar and wind) and 376 MW of waste heat recovery systems by FY28. The presentation says green power consumed plus sold equalled 61% of total power consumption at the consolidated level as of 30 September 2026.

On 29 October 2026, its board approved the acquisition of 26% of SWE Renewables Limited. The company said this would help it meet captive-user requirements, including the minimum 26% equity holding and 51% consumption criteria, and secure access to renewable wind power.

Outlook

With the order, Ambuja Cements’ 150 MW plant is treated as having met the 30 June 2025 cut-off for the ISTS charge waiver, as the committee recommended. The order does not say how the waiver will be applied to past bills. CTUIL did not oppose the petition, having adopted the committee’s findings. Under Regulation 13(2)(h), the waiver applies only because the plant reached COD by the extended date of 8 August 2025.

Official Sources

  1. Central Electricity Regulatory Commission – Order in Petition No. 135/MP/2026, Ambuja Cements Limited vs CTUIL and ESUCRL (18 November 2026): https://cercind.gov.in/2026/orders/135-MP-2026.pdf
  2. Central Electricity Regulatory Commission – Recent Orders 2026 (posting date list): https://cercind.gov.in/recent_orders.html
  3. Ambuja Cements Ltd – Investor Presentation, Q2 FY27 (NSE, 29 October 2026): https://nsearchives.nseindia.in/corporate/AMBUJACEM_29102026143804_ACL_InvestorPresentation.pdf
  4. Ambuja Cements Ltd – Media Release on Q2 FY27 results (NSE, 29 October 2026): https://nsearchives.nseindia.in/corporate/AMBUJACEM_29102026143523_ACL_MediaRelease.pdf
  5. Ambuja Cements Ltd – Outcome of Board Meeting, including acquisition of 26% of SWE Renewables Limited (NSE, 29 October 2026): https://nsearchives.nseindia.in/corporate/AMBUJACEM_29102026142909_ACL_Results_29102926.pdf