The Gujarat Electricity Regulatory Commission (GERC) has extended the scheduled commercial operation date (SCOD) of Solarcraft Power India 3 Private Limited’s 200 MW wind project in Gir Somnath district to 16 May 2025. That adds 36 days to the extensions already granted by Gujarat Urja Vikas Nigam Limited (GUVNL). In an order dated 20 November 2026, the Commission also held that GUVNL may keep termination compensation of ₹18.54 crore for 38.3 MW that was never built. The petition partly succeeded.
Key Details of the Order
The Commission decided Petition No. 2578 of 2025, with two interim applications, filed under the Electricity Act, 2003 and Article 8 of the power purchase agreement (PPA) dated 14 December 2022. The main findings are:
- Project-wide extension: 154 days for force majeure (FM) Events 1 and 2, against the 118 days GUVNL had granted, moving the SCOD from 13 December 2024 to 16 May 2025.
- Long stop date: the last date for commissioning under Article 3.3 of the PPA moves from 7 October 2025 to 12 November 2025.
- Zudvadli cluster: a further extension to 19 June 2025 for delay in state approvals for its transmission line.
- Liquidated damages: GUVNL must recompute damages location-wise for the 161.7 MW commissioned and refund any excess.
- Uncommissioned 38.3 MW: liable for liquidated damages for 180 days, and the default and termination notices stand.
The order does not state the project’s tariff, its cost or the amount GUVNL must refund after recomputing the damages.
The Project and the Bid
GUVNL issued Request for Selection No. GUVNL/500 MW/Wind (Phase III) on 9 May 2022 for 500 MW of grid-connected wind power in Gujarat, with a further 500 MW under a greenshoe option. Solarcraft emerged as a successful bidder and received a letter of intent dated 7 October 2022. The original SCOD was 24 months from the PPA date.
Solarcraft planned 60 wind turbine generators (WTGs) of 3.3 MW each across five clusters: Kansari (69.3 MW), Zudvadli (29.7 MW), Raydi (49.5 MW), Pranchi (26.4 MW) and Bhetali (23.1 MW). The Commission recorded that 49 WTGs, or 161.7 MW, were commissioned between 21 February 2025 and 5 October 2025. The remaining 38.3 MW comprises 23.1 MW at Bhetali, 6.6 MW at Raydi and 6.6 MW at Pranchi, and the Commission noted that 2 MW does not appear to have been planned at all.
Force Majeure Claims
The developer sought an extension of 320 days. GUVNL had granted 71 days by a letter of 16 July 2024 and 47 days by a letter of 18 August 2024, which together moved the SCOD to 10 April 2025.
GERC accepted 138 days for FM Event 1, a change of project site after the Ministry of Defence and the Ministry of New and Renewable Energy (MNRE) returned the no-objection application. The developer said the original locations fell within a low-flying, no-WTG zone, made public only through a National Institute of Wind Energy (NIWE) map published on 13 December 2023. A further 16 days were allowed for FM Event 2, the publication of that map.
The Commission rejected claims for Cyclone Biparjoy, prolonged rainfall and the India-Pakistan hostilities including Operation Sindoor, citing a lack of evidence of actual impact. It also rejected a 90-day claim for installing remote terminal units (RTUs) at each WTG, as required by GERC’s Tariff Order No. 05 of 2024. It noted that the order came about 222 days before the extended SCOD and that no WTG was shown to have been held up.
Cluster-Level Findings
At Kansari, 56.1 MW was commissioned by 10 April 2025 and the remaining 13.2 MW between 23 May and 22 June 2025. GERC found no further relief due there for the line approval and right-of-way claims, so the cluster’s SCOD stays at 16 May 2025.
At Zudvadli, the Commission found that state approval under Sections 68 and 164 of the Act, granted on 16 April 2025, delayed the line. Since 19.8 MW was commissioned on 19 June 2025, it fixed that date as the cluster’s SCOD. Claims for Raydi and Pranchi were rejected, and at Pranchi 19.8 MW was commissioned between 26 September and 5 October 2025.
Damages and Termination
GUVNL recovered ₹20.62 crore in liquidated damages from monthly tariff payments for delay beyond 10 April 2025. Following a default notice of 30 March 2026 and a termination notice of 7 May 2026, it also recovered ₹18.54 crore as termination compensation for the 38.3 MW.
Solarcraft argued that charging both amounted to double recovery. The Commission disagreed. It held that liquidated damages cover delay of up to 180 days, while termination compensation of six months’ billing at the contracted capacity utilisation factor covers the permanent loss of supply. It noted that no FM Event was claimed for Bhetali, which the developer itself foreclosed, and that the developer took part in a fresh bid for the same locations.
Policy Backdrop
GERC’s Tariff Order No. 05 of 2024, the August 2024 tariff framework for wind projects in Gujarat, requires developers to install RTUs at the pooling station and at each WTG at their own cost to send real-time data to the State Load Despatch Centre. The Commission cited its earlier ruling in the Juniper Green Kite case, where it held the RTU rule to be a regulatory compliance requirement rather than an event making performance impossible.
On liquidated damages, the order relied on its 30 December 2024 ruling in SITAC RE Private Limited v. GUVNL. That ruling held that a procurer’s actual loss cannot readily be assessed in money terms, so pre-agreed amounts in the PPA apply.
Outlook
GUVNL must now recompute liquidated damages for each location against the revised dates of 16 May 2025, or 19 June 2025 for Zudvadli, and refund the excess to Solarcraft. The interim applications were disposed of as infructuous. GUVNL also retains the termination compensation, while the liquidated damages for the 38.3 MW remain payable for 180 days under the PPA.
Official Sources
- Gujarat Electricity Regulatory Commission – Order in Petition No. 2578 of 2025, Solarcraft Power India 3 Private Limited vs GUVNL (20 November 2026): https://gercin.org/viewdocument/T3JkZXJzX2ZpbGVzXzU5MjdfMjEtMTEtMjAyNl83NjAxNzEy
- Gujarat Electricity Regulatory Commission – Judgement/Orders list: https://gercin.org/orders/orders_petition/judgement_orders
- Gujarat Electricity Regulatory Commission – Order No. 05 of 2024, Tariff Framework for Procurement of Power from Wind Power Projects (August 2024): https://gercin.org/viewdocument/T3JkZXJzX2ZpbGVzXzI5NV8wNi0wMS0yMDI2XzU0NjQyNzI=