The Madhya Pradesh Cabinet has approved a 200 MW floating solar project with an 800 MWh battery energy storage system as Phase II of the Omkareshwar floating solar park, according to the state government’s official release on the Cabinet meeting of 18 November 2026. The meeting was held at Gandhi Sagar in Mandsaur district. The Omkareshwar floating solar Phase II project is meant to supply power during peak hours, and it will connect to the inter-State transmission system (ISTS).
What the Cabinet approved for Omkareshwar floating solar Phase II
The state’s Department of Public Relations release says the Council of Ministers approved the 200 MW floating solar project, with an 800 MWh battery energy storage system, at the second phase of the Omkareshwar reservoir. The stated purpose is to supply electricity during peak hours. The project will be connected to the ISTS.
The next step is a central approval. After the Ministry of New and Renewable Energy (MNRE) gives its approval, a Bid Process Coordinator will run the bidding through an open tender. The release does not give a tender date, a tariff or a project cost.
In the release, the storage size is given in megawatt-hours (800 MWh). A megawatt-hour figure describes how much energy a battery can store, while the megawatt figure describes how much power the solar plant can produce at a given moment. So the 200 MW plant and the 800 MWh battery are two different measures.
Phase I and the world’s largest single-reservoir claim
The release says Phase I of the Omkareshwar floating solar park, at 278 MW, is complete. It describes Phase I as India’s largest operating floating solar project and one of the largest operating projects in the world. Rewa Ultra Mega Solar Limited developed it at a competitive rate of Rs 3.21 per kWh, and Madhya Pradesh Power Management Company Limited has been buying its electricity since 2024.
Once the 200 MW of Phase II is commissioned, the total capacity at the Omkareshwar reservoir will reach 478 MW, made up of the 278 MW first phase and the 200 MW second phase. According to the release, this could make the Omkareshwar floating solar project the world’s largest floating solar project on a single reservoir. The word “could” is the government’s own, since the second phase has yet to be tendered and built.
The central scheme behind the storage requirement
The release links the project to a central scheme. It says the MNRE has announced the setting up of 5,000 MW of floating solar projects with co-located energy storage of at least two hours under the Pradhan Mantri Surya Sarovar Yojana. To help bring tariffs down, the scheme provides central financial assistance of Rs 1 crore per MW.
The release also cites the National Institute of Solar Energy’s report “Solar PV Potential of India, June 2026”. According to that report, India has a total floating solar potential of 102.18 GW, of which 14.89 GW, about 15 per cent, is available in Madhya Pradesh.
The release does not say whether the Phase II project will use the Rs 1 crore per MW assistance. The scheme and the project are described together, but the release does not link them to a specific amount for Omkareshwar.
What it means for India’s clean-energy sector
Floating solar uses water surfaces instead of land, and a storage system lets the plant supply power after sunset. The Omkareshwar Phase II design pairs both, with 800 MWh of storage for 200 MW of generation. That is equal to four hours of storage if the battery were discharged at the plant’s full 200 MW rating, though the release does not state the discharge duration.
For solar developers, EPC firms and battery suppliers, the open tender that follows MNRE approval will be the point to watch. The approval also shows how a state is using a central scheme to expand renewable capacity at a reservoir that already hosts a completed first phase.
The key facts that remain open are the tender timeline, the tariff, the developer and the commissioning date. Until the tender is issued and awarded, Phase II remains an approved project, not a contracted one.
Official references
1. Government of Madhya Pradesh, Department of Public Relations, Cabinet decisions page: https://mpinfo.org/Home/FrmCabinetDecisions
2. Government of Madhya Pradesh, Department of Public Relations, release on the Cabinet meeting at Gandhi Sagar, 18 November 2026 (Hindi): https://mpinfo.org/Home/CabinetDetails?newsid=%C2%B2%C2%B0%C2%B2%C2%B6%C2%B1%C2%B1%C2%B1%C2%B8%C3%8E%C2%B8%C2%B2&fontname=%C3%8D%C3%A1%C3%AE%C3%A7%C3%A1%C3%AC&LocID=%C2%B3%C2%B2&pubdate=11/18/2026