POWERGRID Commissions 765 kV Transmission Infrastructure for 8.1 GW Rajasthan Solar Evacuation

April 1, 2026 By Gaurav Nathani 2 min read
0:00 / 02:18

Power Grid Corporation of India Limited (POWERGRID) has commissioned the Inter-State Transmission System (ISTS) for the evacuation of 8.1 GW from solar energy zones in Rajasthan. Developed under Phase-II (Parts E and G) through wholly owned subsidiaries, the infrastructure enables the transfer of renewable energy to the national grid using 765 kV corridors.

Phase-II Part-E: POWERGRID Bhadla Sikar Transmission Limited

The Part-E segment of the project was executed by POWERGRID Bhadla Sikar Transmission Limited, a wholly owned subsidiary. The infrastructure for this segment includes a 765 kV double-circuit Bhadla-II–Sikar-II transmission line.

The project was secured through the Tariff-Based Competitive Bidding (TBCB) procurement method. Physical commissioning of the transmission line was completed on January 14, 2026, and the commencement of commercial operation followed on January 16, 2026.

Phase-II Part-G: POWERGRID Narela Transmission Limited

The Part-G segment was implemented by the subsidiary POWERGRID Narela Transmission Limited. This project involved the establishment of a 765/400 kV Gas-Insulated Substation (GIS) at Narela, Delhi, with a transformation capacity of 3×1500 MVA, associated bus reactors, and line bays.

The associated line infrastructure consists of the Khetri–Narela 765 kV double-circuit transmission line, which has a route length of 180 km, and two 765 kV line bays at Khetri. Operational specifications for the Narela substation include the loop-in and loop-out of the 765 kV Meerut–Bhiwani single-circuit line. All project elements were fully commissioned as of December 7, 2025, and the Notification for Commercial Operation (DOCO) was issued on February 24, 2026.

Technical Specifications Summary

Project PhaseSubsidiaryVoltage LevelKey InfrastructureCommercial Operation Date (DOCO)
Phase-II Part-EPOWERGRID Bhadla Sikar Transmission Limited765 kVBhadla-II–Sikar-II D/C lineJanuary 16, 2026
Phase-II Part-GPOWERGRID Narela Transmission Limited765/400 kVNarela GIS (3×1500 MVA) with bus reactors; Khetri-Narela D/C lineFebruary 24, 2026

Regulatory and Contextual Data

  • The projects were secured via Tariff-Based Competitive Bidding conducted by PFC Consulting.
  • The transmission systems are operated under the “build, own, operate, and maintain” (BOOM) model.
  • The Ministry of Power authorized the special purpose vehicle POWERGRID Bhadla Transmission to reroute 36 km of the Fatehgarh II PS-Bhadla II PS 765 kV D/C line to address Great Indian Bustard (GIB) conservation areas.
  • The 765/400 kV Gas-Insulated Substation at Narela has a total transformation capacity of 3×1500 MVA.