BHEL Wins POWERGRID Order for Two Synchronous Condensers at Kalyanpur, Gujarat, Worth ₹600–900 Crore

Bharat Heavy Electricals Limited (BHEL), the state-owned power equipment maker, has won a Power Grid Corporation of India Limited (POWERGRID) award for two +300/-200 MVAR synchronous condensers at Kalyanpur, Gujarat. BHEL told the National Stock Exchange (NSE) on 11 November 2026 that the order is worth ₹600 crore to ₹900 crore, excluding goods and services tax (GST). The units will serve renewable projects in the Jam Khambhaliya renewable energy zone (REZ). It is BHEL’s second synchronous condenser order from POWERGRID in four days.

Key Details

POWERGRID placed the order on behalf of one of its project special purpose vehicle (SPV) companies. BHEL’s disclosure sets out the terms as follows:

  • Scope: design, engineering, manufacturing, supply, erection, testing and commissioning of two +300/-200 MVAR synchronous condensers
  • Location: Kalyanpur, Gujarat
  • Purpose: part of the transmission system for integration of power from renewable energy projects in the Jam Khambhaliya REZ
  • Execution period: 35 months
  • Value: ₹600 crore to ₹900 crore, excluding GST
  • Type: domestic order

The filing states that the promoter group has no interest in the awarding entity and that the order is not a related-party transaction. It does not name the SPV, give the exact contract value or state when the 35-month execution period begins. BHEL also has not said which of its manufacturing units will build the machines.

The Barmer-II Order

On 7 November 2026, BHEL disclosed a separate notification of award from POWERGRID, also placed on behalf of a project SPV, for two +300/-200 MVAR synchronous condensers at the Barmer-II high-voltage direct current (HVDC) terminal station. That order carries the same value band of ₹600 crore to ₹900 crore, excluding GST, and an execution period of 44 months. Taken together, the two awards cover four machines of the same rating, one pair for a Gujarat renewable zone and one pair for a Rajasthan HVDC terminal.

Advertisement

Why It Matters

Synchronous condensers are rotating machines that help keep voltage stable on networks carrying large amounts of solar and wind power. In its supplementary information on the results for the second quarter (Q2) of the 2026-27 financial year (FY27), BHEL listed grid integration, through synchronous condenser design for solar power integration, among its diversification initiatives. The same document cites planned national transmission expenditure of about ₹9 lakh crore over 2022-32, including HVDC corridors.

Policy Backdrop

The Kalyanpur order is tied to evacuating power from a renewable energy zone, the clusters of planned solar and wind capacity that India is connecting to the grid through new transmission systems. BHEL’s investor material cites India’s 2030 non-fossil capacity ambition of 500 GW and green hydrogen output of 5 million tonnes as part of the demand for its renewables and hydrogen business. It also projects peak power demand of 270-280 GW in FY27. BHEL says it has more than 14 GW of power equipment delivered abroad and export references in 95 countries.

About the Company

BHEL is a Government of India undertaking headquartered at Siri Fort, New Delhi. According to its Q2 FY27 investor material, it has 15 manufacturing units, eight service centres and about 27,300 employees. It says it has supplied more than 214 GW of installed power equipment and more than 8,50,000 MVA of transmission equipment, and has executed six HVDC projects. Its businesses span thermal, nuclear and hydro power, transmission, rail, defence, coal gasification and green hydrogen. It has supplied 431 hydro utility sets and more than 850 locomotives.

Advertisement

For Q2 FY27, BHEL reported standalone revenue from operations of ₹9,300 crore, up 24% from ₹7,512 crore. Its outstanding order book stood at ₹2,57,571 crore at the end of September 2026, against ₹2,19,641 crore a year earlier, a rise of about 17.27%. The company put transmission orders under execution at about ₹13,600 crore, alongside about ₹6,400 crore in hydro and about ₹16,400 crore in transportation.

For the first half (H1) of FY27, standalone revenue from operations rose 31% to ₹16,998 crore from ₹12,999 crore. BHEL said its key Q2 orders included the Heo and Tato-I hydro packages, 265 main traction transformers, an FR6B gas turbine and green-ammonia and recycle-gas compressors. It reported 2,260 MW of capacity addition in H1 FY27, against a target of 4,790 MW for the full year.

The Company’s Recent Pipeline

  • H1 FY27: secured orders of about ₹30,000 crore, including about ₹4,000 crore in Q2.
  • 14 October 2026: reported Q2 FY27 results, with standalone EBITDA of ₹1,286 crore against ₹763 crore.
  • 4 November 2026: signed contracts with Adani Power Limited to supply boiler, turbine and generator equipment and agreed services for four projects of 2×800 MW each, with each contract valued at ₹5,000 crore to ₹7,000 crore, excluding GST.
  • 7 November 2026: received POWERGRID’s award for two synchronous condensers at the Barmer-II HVDC terminal station, Rajasthan.

Outlook

BHEL has 35 months to commission the Kalyanpur units. It has not said when it will sign the formal contract for the Kalyanpur units with the POWERGRID SPV, and further grid-stability orders linked to renewable energy zones would add to its transmission work. BHEL has not given guidance on how much of its order book it expects to convert into revenue in the second half of FY27.

Official Sources

  1. Bharat Heavy Electricals Limited – Regulation 30 Disclosure: Order from POWERGRID for 2 Nos. +300/-200 MVAR Synchronous Condenser at Kalyanpur, Gujarat (NSE, 11 November 2026): https://nsearchives.nseindia.com/corporate/BHEL_11112026114240_orderpowergrid11112026.pdf
  2. Bharat Heavy Electricals Limited – Regulation 30 Disclosure: Order from POWERGRID for 2 Nos. Synchronous Condenser at Barmer-II HVDC Terminal Station (NSE, 7 November 2026): https://nsearchives.nseindia.com/corporate/BHEL_07112026125946_orderpgil07112026.pdf
  3. Bharat Heavy Electricals Limited – Regulation 30 Disclosure: Contracts with Adani Power Limited for Four 2×800 MW Projects (NSE, 4 November 2026): https://nsearchives.nseindia.com/corporate/BHEL_04112026085754_APLorder04112026.pdf
  4. Bharat Heavy Electricals Limited – Q2 FY2026-27 Results: Supplementary Information (NSE, 14 October 2026): https://nsearchives.nseindia.com/corporate/BHEL_14102026151739_Q227suppl.pdf
Advertisement