Vikram Solar Q2 FY27: 1.7 GW of New Orders, EBITDA per Watt Up 37%, First TOPCon Cells Due in December 2026

Vikram Solar Q2 FY27 results, announced on 14 November 2026, show a quarter of lower volumes but a better business mix. The Kolkata-based solar module maker said it added about 1.7 GW of new orders in the quarter ended 30 September 2026, against 0.8 GW in the first quarter of FY27, and that its absolute EBITDA per watt improved by about 37% over Q1 FY27. The company also said its 9 GW N-type TOPCon solar cell plant at Gangaikondan, Tamil Nadu, is on schedule to make its first cell in December 2026.

The numbers come from a press release filed with BSE and NSE on 14 November 2026, which calls the fall in volumes a “transitory dip”.

Vikram Solar Q2 FY27: what the company reported

Revenue from operations rose 17.7% from the first half of FY26 to the first half of FY27, according to the release. Absolute EBITDA per watt improved by about 37% over Q1 FY27 even though quarterly volumes were lower. Net debt to equity stood at 0.17x on 30 September 2026.

The press release gives no rupee figures for revenue, EBITDA or profit, and no megawatts sold or total order book, so they are not reported here.

Change in the sales mix

The company says the mix of what it sold changed sharply between the first and second quarters:

  • The share of DCR (domestic content requirement) volumes rose from 7.5% in Q1 FY27 to 22% in Q2 FY27. DCR modules are built with Indian-made cells, which makes cell capacity important for any module maker that wants to serve projects with a domestic-content condition.
  • The share of distribution and retail volumes rose from 14% to 44%, which the company says supports better realisation and shorter cash cycles.
  • Dependence on IPP (independent power producer) and government volumes fell.

According to the company, this change in mix supported better realisation, quicker cash cycles and the 37% sequential rise in EBITDA per watt.

Advertisement

1.7 GW of new orders across customer groups

Vikram Solar added about 1.7 GW of new orders in Q2 FY27 from EPC, government, IPP, C&I (commercial and industrial) and mid-market customers. The comparable figure for Q1 FY27 was 0.8 GW. The company says the order inflow is meant to build visibility for higher utilisation of its expanded capacities in the coming quarters. The release does not name the customers or give the value of the orders.

9 GW TOPCon cell plant at Gangaikondan

The most closely watched item in the release is the 9 GW N-type TOPCon cell factory at Gangaikondan in Tamil Nadu. Vikram Solar says it is on schedule to produce its first cell in December 2026, and that the full 9 GW will be commissioned in phases afterwards.

The company expects the plant to strengthen supply-chain control and traceability, support future DCR volumes and reduce dependence on imported cells. Gangaikondan is also the site of the company’s new module factory, which VYQON covered earlier in its report on the 6 GW Gangaikondan gigafactory.

Building on the cell line, Vikram Solar plans 9 GW of ingot and wafer capacity at the same site by FY29. If completed, this would extend its integration from modules to cells to wafers. No investment amount for the cell, ingot or wafer projects is given in the release.

VSL PowerHive: 7.5 GWh battery assembly plant near Chennai

The release also covers energy storage. VSL PowerHive, a wholly owned subsidiary of Vikram Solar, is setting up a battery energy storage system (BESS) assembly plant at Oragadam, near Chennai, with a capacity of 7.5 GWh a year. The plant can be scaled to 15 GWh in later phases and covers about 1.65 lakh sq ft.

Advertisement

Inauguration is slated for January 2027, and commercial operations are expected from April 2027. PowerHive will then also enter battery cell manufacturing, with 7.5 GWh of capacity planned from 2028.

Management outlook for the second half

Chairman and Managing Director Gyanesh Chaudhary said the quarter was one in which the company “strengthened the foundations of the business”. He listed four priorities for the second half of FY27: converting executable orders, improving asset utilisation, delivering higher DCR volumes and commissioning the cell project in a disciplined manner.

Ratings and company profile

India Ratings and Research rates the company’s aggregated bank facilities IND A+/Stable (long term) and IND A1+ (short term). Vikram Solar is headquartered in Kolkata, sells in 39 countries and has 133 authorised distributors. VYQON also covered its Q1 FY 2027 results, which the second-quarter numbers can be compared against.

What it means for India’s clean-energy sector

Vikram Solar’s second quarter shows a module maker moving up the supply chain. Its stated plan is to add cells first, then ingots and wafers, after its module lines. The 9 GW cell plant, with first cells due in December 2026, ties directly to the rising DCR share the company reports in its own sales mix, because DCR volumes depend on domestic cell supply. The battery assembly plant adds a storage business alongside modules, although its timelines run into 2027 and 2028 and the results will depend on execution.

For investors and buyers, the figures to watch are the conversion of the 1.7 GW of new orders into shipments, the timing of the first cells, and whether the higher DCR and retail shares hold.

Official references

  1. Vikram Solar Limited, press release on unaudited financial results for the quarter and half year ended 30 September 2026 (Q2 FY27), filed with BSE (scrip 544488) and NSE (VIKRAMSOLR) on 14 November 2026: https://www.bseindia.com/xml-data/corpfiling/AttachLive/e8cc44dd-c328-485a-8bf6-9cecd4ec0e28.pdf