ACME Solar Subsidiary Signs 150 MW Hybrid PPA with NTPC at Rs 3.21 Per Unit

ACME Alpha Renewables Private Limited, a subsidiary of ACME Solar Holdings Limited, has signed a power purchase agreement (PPA) with NTPC Limited for a 150 MW hybrid power project. The ACME NTPC hybrid PPA falls under NTPC’s Hybrid-IV tranche and carries a tariff of Rs 3.21 per unit. ACME Solar disclosed the agreement to BSE and NSE on 18 November 2026 under Regulation 30 of the SEBI Listing Regulations, along with a press release. The company described the filing as a voluntary disclosure.

Key terms of the ACME NTPC hybrid PPA

The filing sets out the following terms:

  • Buyer: NTPC Limited, a domestic entity.
  • Contracted capacity: 150 MW.
  • Tariff: Rs 3.21 per unit. The press release says this tariff has already been adopted by the Central Electricity Regulatory Commission (CERC).
  • Scheduled Commencement of Supply Date (SCSD): 30 June 2028.
  • Project tenure: 25 years from the SCSD.
  • Nature of contract: Power Purchase Agreement.

The company stated that neither its promoter nor promoter group companies have any interest in NTPC, and that the agreement is not a related party transaction.

Project design: solar, wind and storage across three states

The project is connected to the Inter-State Transmission System (ISTS). According to the press release, it spans three locations: Bhadla in Rajasthan, Jambkhabalia in Gujarat and Mandsaur in Madhya Pradesh. It will combine solar and wind generation with appropriate energy storage solutions.

Advertisement

ACME Solar says the design is meant to deliver reliable and dispatchable power through the day while meeting the offtaker’s power requirements during peak demand hours. Central Transmission Utility (CTU) connectivity for the project has been secured for Jambkhabalia and Mandsaur. The filing does not state that connectivity has been secured for Bhadla.

The company has not disclosed how the 150 MW is split between solar, wind and storage, the size of the battery energy storage system, the date on which the PPA was signed, or the project cost.

Company comment

Nikhil Dhingra, Joint Managing Director and CEO of ACME Solar, said the PPA with NTPC reinforces the company’s focus on delivering reliable renewable power aligned with the evolving needs of India’s energy market. He added that by combining solar, wind and energy storage, the project will help meet peak-hour demand and support India’s clean energy transition. The press release calls the project an important step in the company’s goal to contribute significantly to the transition.

Portfolio after the agreement

According to the company, the under-construction, PPA-locked contracted portfolio now stands at 5,080 MW out of a total 5,380 MW of under-construction contracted capacity. ACME Solar describes itself as a leading integrated renewable energy player with a diversified contracted portfolio of 8,370 MW spanning solar, battery energy storage systems (BESS), firm and dispatchable renewable energy (FDRE), hybrid and wind solutions. Its operational capacity is about 3,190 MW, along with 5.90 GWh of BESS capacity.

Advertisement

The company says its in-house engineering, procurement and construction (EPC) and operations and maintenance (O&M) divisions allow it to handle end-to-end development and plant operations, with the aim of delivering projects on time and cost-effectively while maintaining operating performance.

What it means for India’s clean-energy sector

Hybrid projects that pair solar and wind with storage are one way for utilities to get power that is available over more hours of the day than a standalone solar plant can offer. The ACME NTPC hybrid PPA shows NTPC contracting such capacity in its Hybrid-IV tranche at a tariff of Rs 3.21 per unit, a figure the regulator has already adopted.

For ACME Solar, the agreement moves another project from the bidding stage to a signed contract. With 5,080 MW of its 5,380 MW under-construction contracted capacity now locked in through PPAs, the main open items are construction and commissioning of the projects within their scheduled supply dates, with this project due to begin supply by 30 June 2028.

The split between technologies and the storage capacity are not yet public, so the exact contribution of storage to the project’s peak-hour supply cannot be assessed from the filing.

Official references

  1. ACME Solar Holdings Limited, Regulation 30 filing “Execution of Power Purchase Agreement” with Annexure-A and press release, BSE/NSE, 18 November 2026