ACME Solar Commissions Another 52.32 MW / 209.28 MWh of BESS at 300 MW Bikaner FDRE Project

ACME Solar Holdings Limited has commissioned a further 52.32 MW / 209.28 MWh of the battery energy storage system (BESS) component of its firm and dispatchable renewable energy (FDRE) project in Bikaner, Rajasthan. In a Regulation 30 filing to BSE and NSE dated 17 November 2026, the company said its wholly owned subsidiary, ACME Greentech Seventh Private Limited, commissioned this part on 17 November 2026. The commercial operation date (COD) for it will be 19 November 2026.

The filing is an update to the company’s earlier intimation dated 27 October 2026.

ACME Solar Bikaner BESS: project location and size

The FDRE project is located at Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan. Its BESS component is rated at 300 MW / 1,200 MWh on a discharge-capacity basis. The Power Purchase Agreement (PPA) for the project has been signed with SJVN Limited.

Advertisement

FDRE projects combine renewable generation with storage so that power can be supplied in a firm, dispatchable manner rather than only when the sun is shining. The battery component is the part that allows power to be held back and delivered later.

Cumulative commissioned capacity

With the latest addition, ACME Greentech Seventh Private Limited has reached a cumulative commissioned BESS capacity of 247.67 MW / 990.68 MWh on a discharge-capacity basis. The total installed capacity of the BESS component is 247.67 MW / 1,321 MWh.

The two energy figures differ because they measure different things: 990.68 MWh is the discharge capacity, while 1,321 MWh is the installed capacity. The power rating, 247.67 MW, is the same in both.

Advertisement

Measured against the 300 MW / 1,200 MWh discharge-capacity rating of the BESS component, the cumulative commissioned figures leave a difference of about 52.33 MW / 209.32 MWh. This is simple arithmetic on the filing’s numbers. The filing does not say when the remaining capacity will be commissioned.

What has not been disclosed

The filing does not give the tariff, the project cost, the battery supplier, or the quantity commissioned in the 27 October 2026 intimation. It also does not describe the status of the solar part of the project.

What it means for India’s clean-energy sector

Grid-scale storage attached to renewable plants is becoming a key tool for supplying power during evening and night hours. By commissioning storage in stages, developers can begin supplying part of a project’s capacity while the rest is completed. This update shows ACME Solar adding another block of its Bikaner BESS and moving closer to the 300 MW / 1,200 MWh rating of that component, against a PPA signed with SJVN Limited.

Official references

  1. ACME Solar Holdings Limited, Regulation 30 filing “Update on commissioning of Battery Energy Storage System (BESS) Project”, BSE/NSE, 17 November 2026