CERC GNA Fourth Amendment 2026 Lets 50 MW-Plus Storage and Renewable Projects Seek Non-Solar-Hour Connectivity

The Central Electricity Regulatory Commission (CERC) has notified the CERC GNA Fourth Amendment, formally the Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2026. The regulations were notified on 11 November 2026, and the CERC website lists them under “Latest Regulations” in its update of 13 November 2026. The amendment lets renewable generating stations and energy storage systems of 50 MW and above seek connectivity for non-solar hours, allows full withdrawal of connectivity in delayed cases, and brings forward the return of connectivity bank guarantees.

Background to the CERC GNA Fourth Amendment

CERC first put the draft out for public comment through a public notice dated 20 May 2026, inviting comments and objections until 22 June 2026. The final regulations take effect from their publication in the Official Gazette. They amend the rules for connectivity and General Network Access (GNA) on the inter-State transmission system.

Full withdrawal of connectivity

The amendment allows an entity to withdraw its entire connectivity quantum when the final grant is delayed by two years or more. Partial withdrawal is not allowed. The application must be made within 45 days of the relevant event, either the issue of the final grant or the lapse of the two-year period after the in-principle grant. If the request is accepted, the bank guarantees are returned, but the application fee is forfeited.

Entities whose application window has already lapsed get a one-time period of 30 days after the amendment takes effect to seek withdrawal.

Advertisement

Earlier release of bank guarantees

Bank guarantees for generation capacity, known as Conn-BG2 and Conn-BG3, are now to be returned within one week after one year from the declaration of the Commercial Operation Date (COD). Earlier they were released in instalments over five years. For projects that have already completed one year of operation, the subsisting guarantees are to be returned within one month of the amendment taking effect, once transmission charge dues are cleared.

Non-solar-hour access for storage and renewable projects

The most significant change for the storage sector is connectivity for non-solar hours. Renewable energy generating stations and energy storage systems of 50 MW and above can seek connectivity for non-solar hours at substations where transmission margin is available. The Central Transmission Utility of India Limited (CTUIL) will publish a list of such substations and update it every month. These applications do not trigger fresh transmission augmentation, and applicants share the dedicated transmission system with the original bay holder.

Energy storage systems must have an energy capacity of at least twice their power capacity in MW, or as notified by the Central Electricity Authority. A 200 MW storage system, for example, would need at least 400 MWh. A renewable station paired with a storage system that does not meet this minimum will not have injection scheduling rights under GNA for that storage during non-solar hours. VYQON has earlier reported on the minimum storage duration that CTUIL applies to BESS connectivity applications, which sits alongside this new rule.

Source changes, land and multi-location projects

The amendment permits a second change of energy source, for example adding storage to a wind or solar connection. The fee is Rs 20,000 per MW or Rs 10 lakh per application, whichever is higher, and a higher combined fee applies where a change of land parcel is also needed. Applications for a change of source can now be made up to six months before the firm start date of connectivity, instead of 18 months.

Advertisement

Sub-lease documents between parent and subsidiary entities are now accepted, subject to conditions. For renewable stations spread over several locations under a single Letter of Award or power purchase agreement, the amendment sets out a structured mechanism to seek connectivity at multiple locations. Connectivity obtained through the land route can also be converted to the power purchase agreement route.

Transfers and dual connectivity

GNA can now be transferred when the identified load, generating station or storage system is transferred to, or acquired by, another entity. The amendment also provides for dual connectivity of drawee entities to both the inter-State transmission system and an intra-State transmission or distribution system, for a part quantum of at least 50 MW or for the full quantum.

What it means for India’s clean-energy sector

For battery storage developers, the non-solar-hour route offers a way to use substation margin that is free after sunset without waiting for new transmission lines. The monthly CTUIL list should help developers pick sites. The benefit is limited to substations that actually have margin, because the amendment does not provide for fresh augmentation, so grid availability will remain a key factor in site selection.

For developers holding connectivity that is stuck, the full-withdrawal option and the faster return of bank guarantees free up working capital, and the one-time 30-day window gives older cases a chance to exit. Releasing guarantees one year after COD also lowers the cost of holding projects. The shorter six-month notice and the second source-change option give developers more flexibility to add storage to existing wind and solar connectivity. VYQON has also covered CERC’s earlier graded paid mechanism for extending connectivity milestones, and the two rules together show the commission tightening how connectivity is held and released.

Official references

  1. CERC website, Latest Regulations listing the Fourth Amendment Regulations, 2026
  2. CERC public notice dated 20 May 2026 on the draft Fourth Amendment Regulations, 2026
Advertisement

Discussion (0)

Leave a Comment

CAPTCHA