A consortium led by Kolkata-based Coal India Limited (CIL) has received a letter of intent (LoI) from the Ministry of Heavy Industries (MHI) to set up a plant for sintered rare earth permanent magnets (REPM). The LoI is for a capacity of 1,200 tonnes per annum (TPA), CIL said in a stock exchange filing on 19 November 2026. CIL leads the consortium with NFTDC, and the group was declared the L2 bidder in the tender. The magnets are used in electric vehicles and wind turbines.

Key Details of the Letter of Intent

CIL disclosed the LoI under Regulation 30 of the Securities and Exchange Board of India (SEBI) Listing Regulations. The main terms are:

  • Awarding body: Ministry of Heavy Industries, Government of India.
  • Instrument: Letter of Intent dated 19 November 2026, issued under the Scheme to Promote Manufacturing of Sintered Rare Earth Permanent Magnet.
  • Bidders: CIL as lead member, with NFTDC, declared the L2 bidder (the filing’s term) in a tender run under a Least Cost System.
  • Nature of work: setting up a manufacturing facility for sintered neodymium-iron-boron (NdFeB) magnets through a special purpose vehicle (SPV) under the scheme.
  • Period: 7 years, made up of 2 years of pre-construction and 5 years of operation.
  • Type: domestic; the promoter group has no interest in the awarding entity, and the order is not a related party transaction.

The filing does not give the incentive amount the consortium bid for, the plant location, the investment required or the shareholding in the SPV. It also does not give NFTDC’s full name or say whether other bidders received LoIs.

How the REPM Scheme Works

The Union Cabinet approved the scheme on 26 November 2025 with a financial outlay of ₹7,280 crore, according to the Press Information Bureau (PIB). The outlay comprises sales-linked incentives of ₹6,450 crore on REPM sales for five years and a capital subsidy of ₹750 crore. The scheme aims to build 6,000 TPA of integrated REPM manufacturing in India; PIB writes the unit as MTPA.

Advertisement

PIB said the scheme envisions allocating the total capacity to five beneficiaries through global competitive bidding, with each allotted up to 1,200 TPA. Its total duration is 7 years from the date of award, including a 2-year gestation period and 5 years of incentive disbursement. Integrated facilities must cover conversion of rare earth oxides to metals, metals to alloys, and alloys to finished magnets.

The tender was run as a two-stage Least Cost System on the Central Public Procurement Portal, with technical and financial bids. When it opened on 20 March 2026, MHI said each beneficiary would be allocated between 600 TPA and 1,200 TPA, in multiples of 100 TPA. It said the scheme offers limited assured supply of neodymium-praseodymium (NdPr) oxide from IREL (India) Ltd. to the three lowest bidders.

MHI said on 13 August 2026 that it had received 20 bids and opened the technical bids that day. CIL was among the listed bidders, alongside companies including Lohum Magnets & Energy Solutions Private Limited, Midwest Energy Limited–Midwest Advanced Materials (JV), Prozeal Green Energy Limited and Renew Private Limited.

Why the Magnets Matter

According to the Cabinet release, REPMs are among the strongest permanent magnets and are vital for electric vehicles, renewable energy, electronics, aerospace and defence. The government expects India’s consumption of REPMs to double by 2030 from 2025. In November 2025 it said that demand was met primarily through imports. MHI said in August 2026 that the scheme is expected to significantly reduce import dependence by building a value chain from NdPr oxide to finished magnets.

Advertisement

About Coal India

CIL, a Maharatna company, is listed on BSE and NSE. In a press release on 1 November 2026, it said its coal supplies in October reached 70.3 million tonnes (MT), crossing 70 MT in a month for the first time. Supplies to the power sector reached 57.1 MT in the same month.

CIL’s investor presentation for Q2 FY 2026-27 lists recent solar additions. It said CIL commissioned 200 MW of its 300 MW solar project at Khavda, Gujarat, on 8 July 2026. It also received a commissioning certificate for a 100 MW solar plant at Bhadramali, Gujarat, effective 31 March 2026. CIL said it recorded revenue from the sale of energy for the first time, ₹15.29 crore in H1 FY 2026-27.

The Company’s Recent Pipeline

  • August 2026: CIL incorporated CIL Global Pte. Ltd., a wholly owned subsidiary in Singapore, on 24 August to explore overseas opportunities in critical minerals asset acquisition.
  • September 2026: the draft red herring prospectus for the initial public offering of subsidiary Mahanadi Coalfields Limited (MCL) was filed on 1 September.
  • October 2026: MCL crossed the 20 MT monthly supply mark for the first time, CIL said on 1 November.
  • October 2026: CIL’s results presentation of 30 October said it had been identified as the preferred bidder for the Gadadharpur iron ore block in Kendujhar, Odisha, with estimated resources of 288 MT.

Outlook

Under the scheme, the 7-year term runs from the date of award, and the filing does not say whether the LoI marks that date. PIB said the 6,000 TPA programme is designed for five beneficiaries; the filing does not name the other beneficiaries or their capacities. The filing names no plant site, investment figure or SPV shareholding.

Official Sources

  1. Coal India Ltd – Regulation 30: Bagging/Receiving of orders/contracts – Sintered Rare Earth Permanent Magnet (NSE, 19 November 2026): https://nsearchives.nseindia.in/corporate/COALINDIA_19112026163735_magnet.pdf
  2. Press Information Bureau – Cabinet Approves Rs.7,280 Crore Scheme to Promote Manufacturing of Sintered Rare Earth Permanent Magnets (REPM): https://www.pib.gov.in/PressReleasePage.aspx?PRID=2194687&reg=48&lang=2
  3. Press Information Bureau – Ministry of Heavy Industries invites bids through Global Tender under the REPM Scheme (20 March 2026): https://www.pib.gov.in/PressReleasePage.aspx?PRID=2242811&reg=3&lang=1
  4. Press Information Bureau – Ministry of Heavy Industries receives 20 bids under the REPM Scheme (13 August 2026): https://www.pib.gov.in/PressReleasePage.aspx?PRID=2299078&reg=1&lang=1
  5. Coal India Ltd – Press Release: Coal India Records All-Time High Coal Supplies in October FY’27 (NSE, 1 November 2026): https://nsearchives.nseindia.in/corporate/COALINDIA_01112026160030_pressnov.pdf
  6. Coal India Ltd – Revised Investor Presentation, Q2 FY 2026-27 results (NSE, 30 October 2026): https://nsearchives.nseindia.in/corporate/COALINDIA_30102026145533_revised_presentation.pdf
Advertisement

Discussion (0)

Leave a Comment

CAPTCHA