Solarworld Energy Q2 FY27 Profit Falls 54.9% to ₹41.9 Million on Input Costs; Order Book Reaches ₹38,569 Million

Noida-based Solarworld Energy Solutions Limited, a solar engineering, procurement and construction (EPC) contractor, has reported a 54.9% fall in consolidated profit after tax to ₹41.9 million for the quarter ended 30 September 2026 (Q2 FY27), from ₹92.9 million a year earlier. Total income rose 81.1% to ₹2,549.0 million. The company filed the results on the National Stock Exchange (NSE) on 13 November 2026. It reports an order book of ₹38,569 million and is shifting its business towards battery storage.

Key Details

The press release and investor presentation give these consolidated Q2 FY27 figures:

  • Revenue from operations: ₹2,439.7 million, against ₹1,378.8 million in Q2 FY26
  • Earnings before interest, tax, depreciation and amortisation (EBITDA): ₹151.5 million, down 16.2% from ₹180.8 million
  • EBITDA margin: 5.9%, against 12.8%
  • Basic earnings per share: ₹0.48, against ₹1.24

For the first half (H1) of FY27, total income rose 95.7% to ₹4,329.3 million from ₹2,212.7 million. H1 EBITDA fell 8.7% to ₹358.2 million, and profit after tax fell 38.3% to ₹136.9 million from ₹222.0 million. Total equity stood at ₹8,619.5 million at the end of September 2026, against ₹8,478.0 million at the end of March 2026.

Why Margins Fell

The presentation names three pressures. Raw material prices kept rising, new entrants pushed prices down, and solar EPC activity slowed sharply. It attributes the slowdown to grid connectivity problems that delayed new projects, and to a daytime power surplus that forced generators to back down.

On input costs, the presentation puts the year-on-year rise at 19.93% for aluminium, 36.26% for copper and 67.78% for lithium carbonate as of late September 2026. The rupee weakened 8.16% against the US dollar over the same period. The company has not disclosed how much of the margin fall came from each factor.

Order Book and Battery Storage

The order book stood at ₹38,569 million on 31 October 2026, up from ₹31,548 million on 30 September 2026. Bids submitted total ₹200,180 million. The company said it has secured orders worth ₹12,711 million from NTPC Renewable Energy Limited and NTPC UP Green Energy Limited, for which letters of award are awaited.

Advertisement

Five battery energy storage system (BESS) orders are in execution, all due by 30 June 2027:

  • Rajasthan Rajya Vidyut Utpadan Nigam Limited, Rajasthan: 125 MW / 250 MWh
  • Gujarat Urja Vikas Nigam Limited, Gujarat: 200 MW / 400 MWh
  • NTPC Limited, Maharashtra: 132 MW / 264 MWh and 75 MW / 150 MWh
  • NTPC Limited, Uttar Pradesh: 50 MW / 100 MWh

Together they total 582 MW / 1,164 MWh. The company is targeting a 60:40 revenue mix between BESS and solar EPC. It said all its new solar projects will be paired with storage. It also plans to enter data centre EPC and transmission line work, and is in talks with global companies for a technical tie-up on data centres.

Manufacturing

Solarworld launched residential and commercial and industrial BESS products during the quarter. Its first containerised system is expected to be complete by December 2026, and it has supplied a first 125 kW / 261 kWh system to a customer. Orders in hand cover about 1.4 GW of its 3.4 GW BESS assembly line at Roorkee, Uttarakhand. Management is evaluating a lithium-ion cell manufacturing line.

On 7 September 2026 the board approved a 50:50 joint venture with Rays Power Infra Limited for a 2.4 GW solar cell plant at Mohasa in Narmadapuram district, Madhya Pradesh. The project is estimated to cost about ₹1,000 crore, with Solarworld committing up to ₹420 crore. Commercial production is targeted for June 2027. The venture replaces an earlier plan for a 1.2 GW cell plant at Pandhurana, and the change in use of public issue proceeds was made subject to shareholder approval.

Management Comment

Managing Director Kartik Teltia said India’s clean energy sector is moving beyond capacity addition towards an integrated system covering manufacturing, power conversion and storage. He described the cell venture as a step towards backward integration.

Advertisement

Teltia said the company’s priorities are a larger manufacturing base, a wider product range and disciplined execution and capital allocation.

Policy Backdrop

The presentation, citing the Ministry of Power and the Central Electricity Authority, says new solar projects have since February 2025 had to include at least two hours of storage equal to 10% of installed solar capacity. It also cites viability gap funding for 92 GWh of grid-scale storage under the Power System Development Fund.

On cells, the presentation says domestic-content rules apply to solar projects from December 2026. The company says its own cells would let it bid for such work, including under the PM-KUSUM scheme.

About the Company

Solarworld has more than 13 years of experience and listed on the NSE and BSE in September 2025. It reports a solar project portfolio of over 1.5 GW and a BESS EPC and independent power producer portfolio of over 1.2 GW. At Roorkee it runs a 1.552 GW module plant and, through a joint venture, a 5 GW junction box line.

Recent Pipeline

  • September 2026: the company commissioned a 50 MW AC solar project in Assam and received charging permission for a 200 MW AC / 272 MW DC project at Khavda, Gujarat, according to the press release.
  • 29 September 2026: subsidiary ZNShine Solarworld Private Limited received a purchase order for 96,000 solar panels of 625 Wp each, worth ₹78.75 crore including 5% integrated goods and services tax.

Outlook

The first containerised BESS product, due by December 2026, and the award letters for the two NTPC group orders are the nearest milestones. All five storage orders in execution fall due by 30 June 2027, the same month the cell plant is targeted to start. The company has not given revenue or margin guidance for the rest of FY27.

Official Sources

  1. Solarworld Energy Solutions Limited – Outcome of Board Meeting: Unaudited Financial Results for the Quarter and Half Year Ended 30 September 2026 (NSE, 13 November 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_13112026154554_OutcomeofBM.pdf
  2. Solarworld Energy Solutions Limited – Press Release on Q2 and H1 FY27 Results (NSE, 13 November 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_13112026162612_Pressrelease.pdf
  3. Solarworld Energy Solutions Limited – Investor Presentation, Q2 FY27 (NSE, 13 November 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_13112026161733_Investorpresentation.pdf
  4. Solarworld Energy Solutions Limited – Key Business and Financial Updates (NSE, 30 September 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_30092026185821_Intimation_Management_Update.pdf
  5. Solarworld Energy Solutions Limited – Outcome of Board Meeting: Joint Venture for 2.4 GW Solar Cell Facility (NSE, 7 September 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_07092026225216_OutcomeofBM.pdf
  6. Solarworld Energy Solutions Limited – Receipt of Purchase Order for Supply of Solar Panels (NSE, 30 September 2026): https://nsearchives.nseindia.com/corporate/SUNSHINE123_30092026133846_Intimation.pdf
Advertisement

Discussion (0)

Leave a Comment

CAPTCHA