SECI Issues Tender for 80 MW Short-Term Firm Power for Tripura (TSECL)

April 26, 2026 By Gaurav Nathani 3 min read
0:00 / 03:34

The Solar Energy Corporation of India (SECI) is acting as an intermediary procurer for the Tripura State Electricity Corporation Limited (TSECL) to facilitate the short-term procurement of 80 MW of firm power. This procurement is conducted through a tariff-based competitive bidding process under open access regulations to meet electricity demand in Tripura, with the delivery location designated at the Tripura State Periphery. The tender is open to power generators, utilities, and licensed electricity traders who possess back-to-back agreements with generation sources.

Supply Period and Technical Requirements

The tender includes the following temporal and technical requirements:

  • Supply Period: The power must be delivered over a three-month duration, commencing April 1, 2026, and concluding June 30, 2026.
  • Peak Window: Bidders are required to supply the contracted capacity daily during the peak evening hours of 18:00 hrs to 24:00 hrs.
  • Energy Sources: Permissible sources include non-solar renewable energy or a firm power mix of thermal, solar, wind, hydro, nuclear, hybrid, or energy storage solutions (such as BESS).
  • Capacity Allocation: The total 80 MW capacity will be awarded to a single successful bidder. The minimum bid capacity from a single generation source is 10 MW.

Financial and Security Stipulations

The financial parameters governing participation and performance are summarized below:

ParameterFinancial Requirement
Tender Processing FeeINR 40,000 + GST
Earnest Money Deposit (EMD)INR 7,500 per MW per month (Total: INR 18 Lakhs)
Contract Performance Guarantee (CPG)INR 50,000 per MW per month (Total: INR 1.2 Crores)
SECI Trading Margin*INR 0.07/kWh

*The SECI trading margin is an administrative fee charged to the buying entity (TSECL) and does not constitute a bidder-side requirement for submission or fulfillment.

The EMD must be submitted as a Bank Guarantee (BG) or electronic Bank Guarantee (e-BG). The successful bidder is required to provide the CPG within seven days of selection to maintain contractual compliance.

Operational and Deviation Clauses

The tender establishes specific protocols for transmission costs and supply variances.

Transmission Charges

Responsibility for transmission-related costs is divided at the delivery point. The bidder bears all open access charges and transmission costs required to reach the delivery point (Tripura State Periphery). TSECL is responsible for all costs beyond this point, including transmission withdrawal charges (T-GNA), State Transmission Utility (STU) charges, losses, scheduling charges, and State Load Despatch Centre (SLDC) application fees.

Deviation Settlement

A deviation settlement mechanism manages variances between scheduled energy and actual delivery on a monthly basis. A deviation limit of 15% of the contracted energy is permitted for both the buyer and the seller. If actual scheduling deviates from the contracted energy by more than 15%, the defaulting party must pay compensation to the non-defaulting party. This compensation is calculated at 20% of the tariff for the quantum of the shortfall that exceeds the 15% limit.

Bidding Schedule and Technical Evaluation

The following deadlines apply to the procurement process:

  • Online Bid Submission End Date: May 4, 2026 (18:00 hrs)
  • Offline Bid Submission End Date: May 6, 2026 (18:00 hrs)
  • Technical Bid Opening: May 7, 2026 (10:00 hrs)

The selection process follows a single-stage, two-envelope competitive bidding method, comprising a techno-commercial evaluation (First Envelope) and an Initial Price Offer (Second Envelope). Bidders clearing the technical evaluation will proceed to an e-Reverse Auction (e-RA). The e-RA features an initial duration of 120 minutes, with 10-minute auto-extensions triggered by any lower bids received in the final 10 minutes. The minimum bid decrement is set at INR 0.01.

Discussion (0)

Leave a Comment

CAPTCHA