The Uttar Pradesh Electricity Regulatory Commission (UPERC) has cleared the path for a major expansion of Kanpur’s clean energy infrastructure by approving power purchase agreements (PPAs) and adopting tariffs for 110 MW of grid-connected solar capacity. This approval represents a significant milestone for utility-scale solar development in the state, achieved through a process of transparent competitive bidding.
Vedu Infrastructure Pvt. Ltd. will spearhead the development across the Kanpur Dehat and Kanpur Nagar districts. Under a 25-year contractual framework, the power generated will be supplied to the Uttar Pradesh Power Corporation Limited (UPPCL), addressing the region’s mounting electricity demand while fortifying the state’s renewable energy portfolio.
Project and Tariff Breakdown
The approved 110 MW capacity is split between two distinct utility-scale sites, with the specific tariff and capacity details outlined below:
| Project Location | Key Specifications |
| Kanpur Dehat | 75 MW Capacity; Approved Tariff: ₹2.65/kWh |
| Kanpur Nagar | 35 MW Capacity; Approved Tariff: ₹2.71/kWh |
These projects will be executed through two dedicated Special Purpose Vehicles (SPVs) incorporated by Vedu Infrastructure: Vedu Kanpur Dehat Solar Pvt. Ltd. and Vedu Kanpur Nagar Solar Pvt. Ltd.
Bidding Process and Organizational Structure
The projects were awarded through a Tariff-Based Competitive Bidding (TBCB) process conducted by the Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA). The final tariffs were discovered during an e-reverse auction held in September 2025.
Aligned with the Ministry of New and Renewable Energy’s (MNRE) Solar Parks Scheme, this development utilizes a structured procurement model designed to streamline large-scale solar deployment. By leveraging transparent competitive bidding, the state continues to attract private investment while ensuring cost-effective power procurement for its utilities.
Regulatory Mandates and Economic Context
UPERC’s approval includes several strict regulatory mandates and economic guardrails. The Commission has directed the developer to utilize solar modules and cells that comply with the Approved List of Models and Manufacturers (ALMM) as per MNRE guidelines.
Furthermore, the Commission has established definitive “Change in Law” guardrails to protect the utility and consumers from future price hikes. Notably, the developer has assumed the full financial risk for these projects, as they are ineligible for future compensation related to ALMM requirements or revisions to Basic Customs Duty (BCD). The Commission deemed the tariffs competitive primarily because a reduction in GST on solar power generators improved the project economics, effectively offsetting the lack of BCD and ALMM compensation.
Details to Watch: As the projects move toward the construction phase, several technical and scheduling disclosures are still pending, including:
- The specific module technology to be employed.
- The projected annual energy generation.
- Final commissioning and grid-synchronization dates.
Regional Renewable Energy Status
The 110 MW Kanpur projects are a vital addition to Uttar Pradesh’s expanding solar park pipeline, directly contributing to the 2,000 MW currently classified as “under construction” in the state. This progress occurs against a backdrop of significant national growth; India successfully achieved 197.19 GW of installed renewable energy capacity (excluding large hydro) by the end of September 2025.
According to current Central Electricity Authority (CEA) data, the status of Solar Parks and Ultra Mega Renewable Energy Power Parks (UMREPPs) in Uttar Pradesh is as follows:
- Total Envisaged Capacity: 3,840 MW
- Capacity Under Construction: 2,000 MW
- Capacity Already Commissioned: 430 MW
The approval of these new facilities in Kanpur Dehat and Kanpur Nagar reinforces the state’s role in India’s broader energy transition, providing a sustainable and clean solution to meet the rising demand for electricity across the region.
Official Source Citations
- Uttar Pradesh Electricity Regulatory Commission (UPERC) Order in Petition No. 2360 of 2026: Approval of PPAs and Adoption of Tariffs for 110 MW Solar Projects
- Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) Request for Selection (RfS) Document: Selection of Solar Power Developers for 110 MW Grid Connected Solar PV Projects (RfS No: 01/UPNEDA/Kanpur Solar Park/RfS/2025)
- Central Electricity Authority (CEA), Ministry of Power Status Report on Development of Solar Parks / UMREPPs in the Country (September 2025)
- Uttar Pradesh Power Corporation Limited (UPPCL) Standard Power Purchase Agreement (PPA) for Procurement of Solar Power on Long Term Basis
- Ministry of New and Renewable Energy (MNRE) Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects

Leave a Comment