POWERGRID Capex Guidance for FY27 Set at Rs 37,000-40,000 Crore as H1 Capitalisation Jumps to Rs 9,300 Crore

POWERGRID’s capex guidance for FY27 stands at Rs 37,000-40,000 crore, and Power Grid Corporation of India Limited has reported capitalisation of Rs 9,300 crore in the first half of FY27, against Rs 3,888 crore in the same period of FY26, according to its investor presentation for the Analysts’ and Institutional Investors’ Meet held on 3 November 2026. The company also reported transmission works in hand worth about Rs 2.20 lakh crore as on 30 September 2026.

The presentation was filed with the stock exchanges on 3 November 2026 under Regulation 30 of the SEBI listing rules. The figures are on a consolidated basis. This article looks at the spending, asset-addition and order-book numbers rather than the quarterly profit and dividend figures.

POWERGRID capex guidance FY27: what the company says

POWERGRID’s guidance for FY27 capital expenditure is Rs 37,000-40,000 crore. Capex in H1 FY27 was Rs 16,864 crore, compared with Rs 15,385 crore in H1 FY26. In the second quarter alone, capex was Rs 9,099 crore against Rs 8,404 crore in Q2 FY26.

Capex is the money spent on building new transmission lines and substations. The H1 FY27 figure is about 46 per cent of the lower end of the full-year range and about 42 per cent of the upper end.

Capitalisation more than doubles in the first half

Capitalisation is the value of projects that have been completed and added to the company’s asset base. POWERGRID’s guidance for FY27 capitalisation is Rs 25,000-30,000 crore. The presentation notes that this figure includes assets capitalised as finance lease and excludes foreign exchange rate variation (FERV).

In H1 FY27 the company capitalised Rs 9,300 crore, against Rs 3,888 crore in H1 FY26. For Q2 FY27 the figure was Rs 4,023 crore, against Rs 2,205 crore a year earlier. Reaching the lower end of the full-year guidance would need about Rs 15,700 crore more in the second half.

Advertisement

Elements commissioned in Q2 FY27, including 765 kV lines such as Koppal-II PS to Raichur, Bidar PS to Maheshwaram and Sikar-II to Khetri, added 981 circuit km of lines and 14,600 MVA of transformation capacity. After September 2026, further elements added 2,616 circuit km and 25,100 MVA. VYQON earlier reported on the commissioning of the Koppal-II/Gadag-II renewable energy zone scheme.

In H1 FY27 two tariff-based competitive bidding (TBCB) projects, the Ramgarh-II and Bidar transmission systems, were fully commissioned.

Order book of about Rs 2.20 lakh crore

As on 30 September 2026, POWERGRID had transmission works in hand of about Rs 2.20 lakh crore. Of this, TBCB projects account for Rs 1.95 lakh crore (89 per cent) and projects under the regulated tariff mechanism (RTM) for Rs 0.25 lakh crore (11 per cent). The total includes construction work in progress of Rs 55,419 crore and excludes the Pang-Kaithal HVDC and offshore projects.

Other businesses add smaller amounts, including smart metering at Rs 2,796 crore and battery energy storage (BESS) at Rs 250 crore.

The presentation also says the Pang evacuation scheme, estimated at about Rs 0.31 lakh crore, is being changed to an extra-high-voltage AC (EHVAC) scheme of 3.75 GW. The change was discussed at the 44th meeting of the National Committee on Transmission held on 29 October 2026.

TBCB wins: 11 projects, Rs 8,107 crore annual tariff

Under TBCB, POWERGRID won 11 projects in H1 FY27, with a combined annual tariff of Rs 8,107 crore, according to the presentation (outcomes until 31 October 2026). Nine are inter-state transmission system (ISTS) projects with an annual tariff of Rs 7,664 crore, including Barmer HVDC (Rajasthan REZ Phase-IV, Part 5), Lakadia REZ Phase-II, Kurnool-V REZ Phase-I and the Green hydrogen hub at Kakinada.

Advertisement

Two intra-state projects, Humnabad in Karnataka and 765 kV GIS Pune West in Maharashtra, carry an annual tariff of Rs 443 crore. VYQON has covered the Pune West project win and the Barmer-II transmission project in earlier reports.

Bidding pipeline of about Rs 67,200 crore

Looking ahead, the TBCB bidding pipeline stood at about Rs 67,200 crore as on 31 October 2026. Of this, 28 projects worth Rs 63,086 crore are under bidding: 10 inter-state projects worth Rs 45,620 crore and 18 intra-state projects worth Rs 17,466 crore. A further three projects worth Rs 4,147 crore are yet to be floated, taking the total approved cost to Rs 67,233 crore.

Operations: availability at 99.81 per cent

System availability in H1 FY27 was 99.81 per cent, against 99.83 per cent in H1 FY26, and the company notes this is above the 99.75 per cent level that earns full incentive. Tripping per line was 0.17 in H1 FY27, unchanged from H1 FY26.

What it means for India’s clean-energy sector

For renewable developers, POWERGRID’s capex and order book indicate how much transmission capacity is being built to carry wind and solar power to demand centres. Several listed projects, including the renewable energy zone schemes and the Kakinada green hydrogen hub, are linked to renewable energy evacuation, and the BESS line shows interest in storage alongside wires.

Whether the company reaches its full-year capitalisation guidance of Rs 25,000-30,000 crore will depend on the pace of commissioning in the second half of the year.

Official references

  1. POWERGRID, Q2 & H1 FY27 Investor Presentation, filed with BSE on 3 November 2026
  2. POWERGRID corporate website