NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited, has invited online bids to supply battery containers and grid-forming power conversion systems (PCS) for its 10 GW / 40 GWh battery energy storage system (BESS) projects. The invitation for bids (IFB), numbered NGEL-CS-5853-004(BESS)-9 and dated 9 November 2026, covers a total deliverable capacity of 40.580 GWh in seven blocks. Bids for the NTPC Green 40 GWh BESS tender are due by 8 December 2026 at 15:00 IST, under international competitive bidding.
What NGEL wants to buy
The brief scope of work in the IFB has three parts:
- Supply of lithium iron phosphate (LFP) based containerised battery systems along with grid-forming PCS
- Supervision of erection, installation and commissioning at the project sites, up to the PCS output terminals
- Comprehensive service and maintenance for 15 years from the date of commissioning of each project, through a long-term service agreement (LTSA)
The tender is a supply package. It does not cover the balance-of-system works at the sites. The IFB does not name the project sites or give delivery dates; it says the detailed scope and terms are in the bidding documents. NGEL intends to finance the package through its own resources and/or external borrowings.
NTPC Green 40 GWh BESS blocks and phases
The 40.580 GWh is divided into seven blocks across three phases:
- Block B-1, Phase 1: 4.980 GWh
- Block B-2, Phase 1: 6.600 GWh
- Block B-3, Phase 1: 5.840 GWh
- Block B-4, Phase 2: 4.560 GWh
- Block B-5, Phase 3: 5.800 GWh
- Block B-6, Phase 3: 6.800 GWh
- Block B-7, Phase 3: 6.000 GWh
That makes 17.420 GWh in Phase 1, 4.560 GWh in Phase 2 and 18.600 GWh in Phase 3. A bidder may quote for any one block, more than one, or all blocks, in any one or more phases. The minimum quantity is one block, and each block must be quoted for its full capacity. A bid for part of a block will be rejected.
Bidding process and key dates
The tender follows a single-stage, two-envelope process. Envelope I is the techno-commercial bid, with nil deviation, and Envelope II is the price bid. Bidders must register on the ETS e-tender portal, where the tender search code is NGEL-2026-TN000012, and must submit a signed non-disclosure agreement before they are authorised to download the documents. The bidding documents are free of cost.
- IFB date: 9 November 2026
- Download of bidding documents: 12 November to 23 November 2026
- Pre-bid conference and last date for queries: 24 November 2026
- Last date for techno-commercial and price bids: 8 December 2026, 15:00 IST
- Opening of techno-commercial bids: 8 December 2026, 15:30 IST
- Opening of price bids: to be intimated separately
Bid security and financial criteria
Bid security depends on the capacity quoted. It is Rs 50 crore for any combination of blocks up to 5 GWh, Rs 100 crore from 5 GWh to 10 GWh, and Rs 200 crore above 10 GWh.
On the financial side, the bidder’s average annual turnover over the preceding three financial years must be at least Rs 69 lakh multiplied by the total capacity quoted in MWh. For the smallest block, 4,560 MWh, that works out to about Rs 3,146 crore. Net worth must be at least 25% of paid-up share capital, and must not have eroded by more than 30% in the last three financial years.
Who can bid
The main technical route is for battery makers. The bidder should have manufactured and supplied LFP containerised battery systems with a cumulative capacity of at least 4,000 MWh, in one order or a maximum of 10 orders, during the last three years. At least one supply order should be of 500 MWh or more, delivered at a single location.
Indian companies have several other routes, each of which requires an association with a qualified manufacturer that meets the 4,000 MWh requirement, backed by a joint undertaking for performance of the contract. These routes are open to an Indian company that has:
- manufactured and supplied at least 80 MWh of containerised battery systems for grid-interactive storage, including one order of 20 MWh or more
- supplied and commissioned grid-interactive BESS of at least 80 MWh, including one system of 20 MWh or more
- built grid-connected solar or wind plants of 40 MW AC or more, including one plant of 10 MW AC or more
- executed an industrial project and a substation of at least 33 kV as developer or EPC contractor in the last ten years
Group, holding or subsidiary companies of qualified firms can also bid, with a joint undertaking.
What it means for India’s clean-energy sector
The 40.580 GWh tender shows NGEL separating battery and PCS supply from site works. On the same date, NGEL issued a separate balance-of-system tender for a 250 MW / 1,000 MWh BESS at NTPC Kayamkulam in Kerala, in which the batteries and PCS are supplied by the owner. VYQON earlier covered the plan for battery storage at Kayamkulam.
The 15-year LTSA ties the supplier to the long-term performance of the batteries. The qualification rules open the tender to global LFP manufacturers while giving Indian battery, renewable and EPC companies a way to take part through tie-ups. Prices will be known only after the price bids are opened.