NTPC Kayamkulam BESS: NTPC Green Invites Bids for BoS Package of 250 MW / 1,000 MWh Project in Kerala

NTPC Green Energy Limited (NGEL), a subsidiary of NTPC Limited, has invited online bids for the balance-of-system (BoS) package of a 250 MW / 1,000 MWh battery energy storage system (BESS) at NTPC Kayamkulam in Kerala. The invitation for bids (IFB), numbered NGEL-CS-5831-004(BESS BOS)-9, is dated 9 November 2026. Bids for the NTPC Kayamkulam BESS package are due by 11 December 2026 at 14:00, under domestic competitive bidding followed by a reverse auction.

What the BoS package covers

The successful bidder will design, engineer, supply, transport, unload, store, build, erect, test and commission the grid-connected 250 MW / 1,000 MWh BESS on a turnkey basis. The package excludes the supply of the BESS DC containers and the grid-forming power conversion systems (PCS).

The containerised battery system and the PCS will be free-issued by the owner. The bidder must still move them: inland transport from the Indian port to the site, including loading and unloading, is in the bidder’s scope, and the bidder has to engage a customs broker for clearance at the incoming port. The supply of the batteries and PCS, and the supervision of their erection and commissioning, remain with the owner.

The bidder’s scope includes these major items:

  • Energy management system (EMS) and SCADA, protection, communication, monitoring and control systems
  • HT and LT systems, PCS transformers, power transformers and the auxiliary power supply for the whole plant
  • Fire fighting, earthing, lightning protection, illumination and CCTV covering 100% of the block periphery
  • Site grading, internal roads, drainage, a control room with switchgear room, and civil works for the batteries and PCS
  • Grid compliance study, reactive power compensation and power quality compliance up to the 220 kV grid interconnection point
  • Mandatory spares, documentation and training for operators and maintenance staff

The bidder must also obtain site-specific data from the owner to prepare its installation plans.

Advertisement

NTPC Kayamkulam BESS: a single 220 kV block

The project will be built as a single block, Block-1, of 250 MW / 1,000 MWh integrated at the 220 kV level. The capacity is the rated AC discharge capacity at the point of injection or metering. For this reason, the cumulative nameplate capacity of the batteries and PCS free-issued to the bidder will be 15% more than the AC discharge capacity.

The scope includes a new 220 kV air-insulated switchyard with 220/33 kV power transformers, pooling switchgear and the power evacuation system up to the 220 kV transmission line take-off gantry. The switchyard will have incoming and outgoing line arrangements through two 220 kV line bays, as a loop-in loop-out (LILO) of the existing Kundra line. The LILO of the existing 220 kV line to the take-off gantry at the plant boundary will be done through a separate package.

The metering philosophy must follow the requirements of KSEBL and the site, and the metering system is in the bidder’s scope. The plant must be in line with the latest guidelines of CEA, CERC and the load despatch centre.

Design life and O&M

The designed life of the BESS plant must be at least 15 years from the successful completion of the trial run. The bidder will carry out comprehensive operation and maintenance of the plant, with electrical equipment, consumables and spare parts, for five years from the commissioning of the full project capacity.

For the batteries and PCS, the owner will arrange a separate comprehensive annual maintenance contract covering periodic and corrective maintenance. This is excluded from the bidder’s scope.

Advertisement

Bidding process and key dates

The tender follows a single-stage, two-envelope process, with Envelope I for the techno-commercial bid and Envelope II for the price bid, followed by a reverse auction. The NTPC tender portal classifies it as a work contract.

  • IFB date: 9 November 2026
  • Document sale starts: 16 November 2026, 17:00
  • Document sale closes: 27 November 2026, 17:00
  • Bid submission ends: 11 December 2026, 14:00
  • Bid opening: 11 December 2026, 14:30

The abridged IFB does not give the estimated cost, the bid security or the completion period; these are in the detailed bidding documents.

What it means for India’s clean-energy sector

The tender shows how NGEL is splitting large storage projects into two parts. On the same date, it invited international bids for the supply of 40.580 GWh of LFP battery containers and grid-forming PCS for its 10 GW / 40 GWh BESS projects, with a 15-year service agreement, covered by VYQON here: NTPC Green 40 GWh BESS tender. The Kayamkulam BoS package is the site-side half of that model, open to domestic contractors who integrate owner-supplied batteries and PCS.

For Kerala, a 1,000 MWh battery connected at 220 kV adds four hours of storage at 250 MW. VYQON earlier reported on the state’s plan with NTPC for battery storage at Kayamkulam. For EPC and electrical contractors, the package is a 220 kV switchyard, integration and five-year O&M job, with the battery technology risk kept by the owner.

Official references

  1. NTPC Tender Portal, NIT details for NGEL-CS-5831-004(BESS-BOS)-9: https://ntpctender.ntpc.co.in/NITDetails/NITs/30487
  2. NTPC Green Energy Limited, abridged Invitation for Bids and brief scope of work, BoS package for 250 MW / 1,000 MWh BESS at NTPC Kayamkulam, dated 09.11.2026: https://ntpctender.ntpc.co.in/Uploads/job_46132.pdf
  3. NTPC Green Energy Limited, Invitation for Bids NGEL-CS-5853-004(BESS)-9 (battery containers and grid-forming PCS): https://ntpctender.ntpc.co.in/Uploads/job_46133.pdf