ACME Solar Holdings Limited has commissioned the first 63.78 MW / 255.120 MWh of discharge capacity of the battery energy storage system (BESS) at its 280 MW / 1,120 MWh NHPC firm and dispatchable renewable energy (FDRE) project in Jaisalmer, Rajasthan. The company’s wholly owned subsidiary, ACME Hybrid Urja Private Limited, commissioned this capacity on 25 November 2026, according to a stock exchange filing the same day. The commercial operation date (COD) for this portion is 27 November 2026.
ACME Solar NHPC FDRE battery storage: what was commissioned
In its Regulation 30 filing to BSE (scrip code 544283) and NSE (symbol ACMESOLAR), ACME Solar gave these details:
- Subsidiary: ACME Hybrid Urja Private Limited, a wholly owned subsidiary.
- Commissioned discharge capacity: 63.78 MW / 255.120 MWh.
- Installed capacity of this portion: 63.78 MW / 300.00 MWh.
- Total BESS component of the project: 280 MW / 1,120 MWh of discharge capacity, with 280 MW / 1,316 MWh installed.
- Location: Village Mehar Nagar, Tehsil Pokaran, District Jaisalmer, Rajasthan.
- Commissioning date: 25 November 2026; COD on 27 November 2026.
- Offtaker: a power purchase agreement (PPA) has been signed with NHPC Limited.
The company said that, at present, only the BESS component of the project has been commissioned. The filing does not give a tariff or say when the solar or other components will be commissioned, so those details are not reported here.
Discharge capacity and installed capacity
The filing quotes two sets of figures for the battery system. Discharge capacity is the energy the system can deliver to the grid, while installed capacity is the larger amount of battery installed to allow for losses and degradation over time. For the first 63.78 MW tranche, the commissioned discharge capacity is 255.120 MWh against 300.00 MWh installed. For the full 280 MW system the filing gives 1,120 MWh of discharge capacity against 1,316 MWh installed.
Background: the NHPC FDRE project
FDRE projects combine renewable generation with storage so that a buyer receives power in a steadier, more dispatchable pattern than plain solar or wind can offer. ACME Hybrid Urja is the ACME Solar subsidiary behind the 280 MW FDRE project contracted with NHPC. In August 2025 it was reported to have secured about Rs 3,184 crore in long-term financing from REC for the project.
Second filing: Chittorgarh project
On the same day, ACME Solar filed an update on a separate project. Through its wholly owned subsidiary ACME Sigma Urja Private Limited, it additionally commissioned 14.55 MW / 60.387 MWh of discharge capacity (installed 14.55 MW / 65.195 MWh) of the 50 MW / 209 MWh Tata Power FDRE project at Village Neemri, Tehsil Rawatbhata, District Chittorgarh, Rajasthan, on 24 November 2026, with COD on 26 November 2026. The PPA for that project is with The Tata Power Company Limited. With this, the subsidiary’s cumulative commissioned BESS discharge capacity at the project is 50.36 MW / 209.032 MWh (installed 50.36 MW / 225.675 MWh). VYQON has reported on earlier commissioning at that project, including ACME Solar’s 35.81 MW / 148.645 MWh commissioning for the Tata Power FDRE project in Chittorgarh.
What it means for India’s clean-energy sector
Battery storage is central to FDRE contracts, because the stored energy lets a project supply power at the times a buyer needs it rather than only when the sun shines or the wind blows. Commissioning in stages, as ACME is doing here, allows each tranche to start earning once it reaches COD instead of waiting for the full 1,120 MWh to be ready. Rajasthan, with its large solar parks, is a natural location for such projects, and a utility buyer such as NHPC gains a source of firm renewable power. As more of the 280 MW system is commissioned, the company is expected to report it to the exchanges through further Regulation 30 filings.
Official references
- ACME Solar Holdings Limited, Regulation 30 intimation on commissioning of Battery Energy Storage Systems (BESS) project, NHPC FDRE project, BSE and NSE, 25 November 2026
- ACME Solar Holdings Limited, Regulation 30 update on commissioning of BESS, Tata Power FDRE project, Chittorgarh, BSE and NSE, 25 November 2026