Diamond Power Wins Further Rs 488.18 Crore Adani Energy Orders for 6,660 km of Conductors on Bhadla-Fatehpur HVDC Line

Diamond Power Infrastructure Limited has received two further purchase orders from Adani Energy Solutions Limited (AESL) worth Rs 488.18 crore including GST for AL-59 conductors for the Bhadla-Fatehpur HVDC transmission line. The orders, received on 25 November 2026, cover 6,659.66 km of conductors for the Uttar Pradesh and Madhya Pradesh portions of the +/-800 kV project. The Diamond Power Bhadla-Fatehpur HVDC conductor orders follow an earlier Rs 707.80 crore order for the same line.

Diamond Power Bhadla-Fatehpur HVDC conductor orders: key details

In its Regulation 30 filing to BSE (scrip code 522163) and NSE (symbol DIACABS) and an accompanying press release, the company set out the following terms:

  • Customer: Adani Energy Solutions Limited, a domestic entity.
  • Order value: Rs 488.18 crore including 18% GST; the basic value is Rs 413.71 crore excluding GST, including packing, forwarding, freight and transit insurance.
  • Quantity: 6,659.66 km of AL-59 conductors, made up of 5,692.66 km of AL-59 Lapwing and 967 km of AL-59 Zebra.
  • Scope: design, engineering, manufacture, testing, packing and supply on a delivered-at-site basis for the Uttar Pradesh and Madhya Pradesh portions of the line.
  • Delivery: month-wise as per project requirement, to be completed on or before 31 December 2027.
  • Other terms: performance security by way of a corporate guarantee and a defect liability period of 18 months, lot-wise.

The company said the orders were received in the ordinary course of business. They are not related-party transactions, and its promoters, promoter group and group companies have no interest in the customer.

A follow-on order for the same line

These orders add to the Rs 707.80 crore order that VYQON reported on 20 November 2026 (see Diamond Power HVDC conductor order for the Bhadla-Fatehpur line). According to the company, the two sets of orders together take its total for the Bhadla-Fatehpur HVDC line to about Rs 1,196 crore including GST.

Advertisement

About the Bhadla-Fatehpur HVDC project

The Bhadla-Fatehpur HVDC link is being developed by Adani Energy Solutions as a +/-800 kV, 6,000 MW corridor of about 950 km. It connects Bhadla in Rajasthan with Fatehpur in Uttar Pradesh and is meant to carry renewable energy from Rajasthan to demand centres in northern India. The company’s press release describes it as one of India’s largest green energy corridors.

HVDC, or high-voltage direct current, is the technology used to move very large blocks of power over long distances with low losses. According to the press release, +/-800 kV is the highest HVDC voltage level in operation in India, and conductors for such lines are large-diameter, high-capacity products that must meet demanding quality and surface-finish requirements. They are supplied by a limited set of qualified manufacturers.

Company comment and capability

Kavish Shah, Vice President – Corporate Strategy at Diamond Power, said the repeat orders reflect the continued confidence AESL has placed in the company. He said that with integrated aluminium rod mills, expanded conductor capacity and in-house testing facilities, the company is well placed to execute on schedule and to take part in the HVDC and green energy corridor projects being planned across the country.

Advertisement

Diamond Power describes itself as one of the largest conductor manufacturers in India. Its conductor range covers ACSR, AL-59, AAAC and HTLS conductors, and its plant at Vadodara is supported by NABL-accredited in-house laboratories with high-voltage test facilities rated up to 765 kV. The company also makes LV, MV, HV and EHV power cables, solar DC and EV charging cables, and serves power, infrastructure, oil and gas, renewables, real estate and data centre customers.

What it means for India’s clean-energy sector

Large renewable energy parks in Rajasthan can add generation faster than the grid can carry it to consumers, so long-distance transmission corridors are a precondition for using that power. A 6,000 MW HVDC link of about 950 km is designed to move a large volume of solar and wind output to northern demand centres with limited losses. Orders for conductors are an early sign that equipment supply for such a corridor is moving from award to manufacture, and the month-wise deliveries running to 31 December 2027 show the supply schedule the project is working to.

The filing does not give a commissioning date for the line or the timing of the Rajasthan portion, so those are not reported here.

Official references

  1. Diamond Power Infrastructure Limited, Regulation 30 intimation and press release on orders aggregating Rs 488.18 crore for AL-59 conductors, BSE and NSE, 25 November 2026
Advertisement