Advait Energy Transitions Limited has received two turnkey orders worth about Rs 131.58 crore in total from Dakshin Gujarat Vij Company Limited (DGVCL) to convert overhead power lines to underground cable in the Bardoli and Vyara divisions of Gujarat. The company said it received both orders on 3 November 2026 and informed the BSE and NSE on 4 November 2026. For Advait Energy, the DGVCL order from the Bardoli division is valued at Rs 69,52,58,019.69 including taxes, and the Vyara division order at Rs 62,05,32,098.04 including taxes. Together the two orders come to Rs 131,57,90,117.73, or about Rs 131.58 crore.
What the two Advait Energy DGVCL orders cover
Both contracts are turnkey, which means Advait Energy is responsible for the whole job from the first survey to the final documentation. According to the company’s filings, the scope for each division includes:
- A site survey, including verification of underground utilities using ground-penetrating radar (GPR) and EPL.
- Design, engineering, procurement, supply, transport, installation, testing, commissioning and documentation.
- Conversion of the existing 11/22 kV high-tension (HT) overhead network to an underground cable system, with SCADA-compatible ring main units (RMUs).
- Removal of the DO (drop-out) overhead system.
- Higher-capacity transformers and SCADA-compatible compact substations (CSS).
- Conversion of the overhead low-tension (LT) network to underground using FSP/MSP.
- GIS Mapping / Geo Urja Mapping, which was developed by GUVNL, and asset tagging.
The filings describe the work as conversion of the existing 11/22 kV HT and LT overhead network to an underground cable system under the SI scheme (Robust 3). The orders were placed by DGVCL, a domestic entity.
Timeline and order terms
Each order is to be executed in 24 months, excluding the monsoon period of June, July and August, after a commencement period of 45 days. The filings do not give a start date for the work, so the calendar completion date is not known from the disclosure.
Advait Energy also stated that its promoter, promoter group and group companies have no interest in DGVCL, which awarded the orders, and the filings show no entry for related-party transactions. In plain terms, the orders were awarded in the normal course of business and are not related-party deals.
The filings do not disclose the length of cable to be laid, the number of transformers, RMUs or compact substations, or the number of consumers covered. This article therefore does not quote any such figures.
What it means for India’s distribution sector
Moving 11/22 kV and LT lines underground, adding SCADA-compatible switchgear and mapping every asset on a GIS system are all steps towards a more monitored and controllable distribution network. SCADA-compatible RMUs and compact substations allow a utility to monitor and operate parts of its network remotely, and underground cable removes the exposure of bare overhead lines. The scope of these two orders shows that the work is being packaged as a single turnkey contract per division, covering survey, design, supply, installation and mapping.
For a listed engineering and cable company such as Advait Energy, the two DGVCL orders add Rs 131.58 crore of work in southern Gujarat with a defined 24-month execution window. Whether and how the orders change the company’s order book or earnings has not been stated in the filings, and it is not assessed here.