The Central Electricity Authority (CEA) has issued a standard operating procedure (SOP) for repowering wind power projects that will run a mix of old and new wind turbine generators (WTGs) under its grid connectivity regulations. The seven-page document, file reference CEA-PS-11-17/2/2023-PSPA-I Division I/70826/2026, was listed on the “What’s New” page of the CEA website on 19 November 2026. The wind repowering SOP explains how such plants should prove grid compliance, which studies they must submit and what equipment they must install at the point of interconnection.
What the wind repowering SOP is based on
The SOP follows the CEA (Technical Standards for Connectivity to the Grid) Regulations, 2007 and their later amendments, and the National Repowering and Life Extension Policy for Wind Power Projects, 2023, which the Ministry of New and Renewable Energy (MNRE) issued on 7 December 2023. It defines repowering as the replacement of old or legacy WTGs with new WTGs at an existing site, in line with the applicable MNRE or state policy.
The background section repeats the MNRE eligibility criteria: turbines that miss quality control orders, have completed their design life, are rated below 2 MW, or are older than 15 years (voluntary), plus turbines with malfunctions or safety concerns.
Who the SOP applies to
The SOP applies to repowering plants across the country that are governed by MNRE’s repowering policy for wind projects. It also applies to partly commissioned plants that want to use their connectivity up to the quantum granted by the Central Transmission Utility of India Limited (CTUIL) or the State Transmission Utility (STU), subject to consultation with the DISCOM, STU or CTU on system feasibility and network conditions.
Legacy turbines commissioned on or before the 2019 amendment of the connectivity regulations are to be grandfathered and need not be retrofitted to current standards, except as the SOP provides. The document grants no relaxation from the rules that applied at the time of their commissioning, says their compliance will not be assessed through simulation studies at this stage, and requires them to keep meeting regulatory requirements during real-time grid operation. Where dedicated infrastructure is shared with solar or battery storage, compliance follows the existing CEA regulations and verification procedure.
Point of interconnection
Compliance is measured at the point of interconnection (POI). For plants connected to the inter-state transmission system, the POI is the ISTS substation at which connectivity has been granted under the CERC GNA Regulations. For intra-state and DISCOM-connected plants, the SOP lists four cases, A to D, depending on voltage and on who owns the terminal bay and line.
Metering and recorders
A power quality meter (PQM) is to be installed at the terminal bay at the POI in all cases. The plant must also install a disturbance recorder (DR) or digital fault recorder (DFR), either at the POI or at each new WTG commissioned after the February 2019 amendment. The SOP links these requirements to the CEA’s 2026 amendment to its technical standards for construction of electrical plants and electric lines.
Simulation studies and compliance
For steady-state studies, active and reactive power from old turbines that do not comply with the present regulations is to be taken as zero injection. This treatment lasts only until the earliest of repowering completion, the end of project life, or expiry of the valid power purchase agreement or energy wheeling agreement. After that, every WTG in the plant, replaced or not, must show full compliance or be decommissioned or repowered.
Developers must submit study reports and simulation models following the CTU list of studies. The SOP specifies detailed RMS (root mean square) models for reactive power assessment and detailed EMT (electromagnetic transient) models for power quality assessment, plus aggregated RMS and EMT models for dynamic studies of the new turbines. New turbines must also meet the design temperature requirements for delivering rated power under existing Ministry of Power and CEA guidelines.
If the studies show a need, the plant must install extra devices such as reactive power resources and harmonic filters. Harmonic filter replacement can be done in batches, each covering at least 33% of the project’s installed capacity. Until the required compliance is achieved, the plant may schedule injection at the POI only up to its compliant capacity. Mitigation measures must be in place before physical interconnection with the grid, and developers need not wait for model verification by the nodal agency.
As-built model validation
Validating the complete plant model after new turbines are installed may not be feasible at this stage, so validation follows each repowered batch of at least 33% of installed capacity. In the interim, the plant submits periodic PQM, DR or DFR data and partly validates its model at each replacement milestone; full validation is due when the whole repowering is complete.
What it means for India’s wind sector
The SOP gives developers and grid agencies a common procedure for plants where old non-compliant turbines keep operating beside new ones during phased repowering. The zero-injection treatment of old turbines in studies, the grandfathering of legacy machines and the batch-wise 33% milestones are designed to let repowering proceed in stages. The document does not state any capacity target or timeline, and old turbines are not excused beyond repowering completion, project life or PPA expiry.
Official references
- Central Electricity Authority: SOP for Repowering of Wind Power Projects with Mixed WTGs under the CEA Connectivity Regulations (file ref. CEA-PS-11-17/2/2023-PSPA-I Division I/70826/2026), https://cea.nic.in/whats-new/file?path=%2Fhome%2Fcea_website%2Freports%2Fgeneral%2Fhi%2FCEA_SOP_Repowering_Wind_Power_Projects_1795063521629.pdf&mode=view