The Central Electricity Regulatory Commission (CERC) has ruled that the part of Zenataris Renewable Energy Private Limited’s 171.6 MW wind-solar hybrid project that reached commercial operation by 30 June 2026 qualifies for a waiver of inter-state transmission system (ISTS) charges. The same order denies the waiver for 5.6 MW of wind capacity that was commissioned only on 30 August 2026. The Commission decided Petition No. 246/MP/2026, along with Interim Application No. 82/2026, on 18 November 2026, and the order was posted on the CERC website on 20 November 2026.
The bench consisted of Chairperson Jishnu Barua and Members Ramesh Babu V., Harish Dudani and Ravinder Singh Dhillon. The respondent was the Central Transmission Utility of India Limited (CTUIL).
The Zenataris 171.6 MW ISTS waiver at a glance
Under the order, the capacity that actually achieved commercial operation date (COD) on or before 30 June 2026 will be treated as if it had reached COD on or before 30 June 2025. That earlier date matters because eligible wind, solar and hybrid projects commissioned by then get a waiver of ISTS charges under Regulation 13(2)(h) of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020.
The 5.6 MW of wind that missed 30 June 2026 is not eligible for any relief under that regulation. The National Load Despatch Centre (NLDC) must verify the COD certificates for the capacity that met the date before the waiver is considered. The petitioner had also asked that its scheduled commissioning date be extended until the common transmission line is commissioned. The Commission rejected this, because the 2020 regulations contain no such provision.
About the project
Zenataris is developing a 300.3 MW wind-solar hybrid project in Vijayanagara district, Karnataka, made up of 66 MW, 171.6 MW and 62.7 MW parts, for sale to third parties under a bilateral or group captive arrangement. This petition covers only the 171.6 MW part: 100 MW of solar and 71.6 MW of wind.
CTUIL gave final grant of connectivity for the 171.6 MW on 8 March 2024, with a start date of 30 June 2025, at the Hiriyur substation. It is linked to the Narendra (New)-Pune 765 kV double-circuit line, a common transmission system (CTS) line.
The company told the Commission it has invested about Rs 1,700 crore, including a 93.48 km dedicated transmission line, a grid substation, 46 wind turbine generators delivered to site (42 installed) and 758 acres acquired for the solar part.
How the extensions came about
The developer approached the committee formed under Regulation 13(2)(h). Its report of 27 October 2025 recommended a six-month extension from 30 June 2025, or until the CTS was commissioned, whichever was earlier. It cited delay in the CTS line, local obstruction, right-of-way issues and an exceptionally heavy monsoon. A second report, dated 18 March 2026, recommended a further extension to 30 June 2026 on the same basis. The committee noted that the plant was physically complete, CEA energisation approvals were in hand and the developer’s dedicated line up to Hiriyur was in place.
The regulation allows extensions of up to six months at a time, and not more than twice. The CERC listed three conditions for the waiver: a scheduled commissioning date on or before 30 June 2025, a delay caused by force majeure, including non-availability of the transmission system, and commercial operation by the extended date.
Commissioning status and the transmission line
The petitioner told the Commission that the remaining 5.6 MW of wind was commissioned on 30 August 2026, and that the delay came from the non-commissioning of the CTS needed to operationalise its connectivity. During the 22 September 2026 hearing, the Commission noted that the connectivity covered 71.6 MW of wind and 100 MW of solar, and asked the petitioner to clarify on affidavit the capacity declared at COD for each component, with dates and certificates. This is why the NLDC check forms part of the ruling.
CTUIL told the Commission in an affidavit of 21 September 2026 that the connectivity is linked to the ISTS Network Expansion Scheme in the Western and Southern Regions for export of surplus power during high renewable energy scenarios in the Southern Region. The transmission service provider, WRSR Power Transmission Limited, is implementing it, with an anticipated commissioning date of December 2026.
What it means for India’s clean-energy sector
The ruling shows how the CERC applies the 30 June 2025 cut-off for the ISTS waiver. Developers whose projects were ready but held up by late transmission can still qualify if they reach commercial operation within the extended date approved on the committee’s recommendation. A project that misses that date, as the 5.6 MW of wind did here, loses the waiver for that capacity.
For the developer’s customers under the bilateral or group captive arrangement, the waived capacity will not attract ISTS charges once the NLDC has verified the COD certificates. The order does not state the monetary value of the waiver.
VYQON has also reported on CERC’s refusal of an ISTS waiver extension to Tata Power Renewable’s wind and solar projects after a missed 30 June deadline.
Official references
- CERC, Order in Petition No. 246/MP/2026 along with IA No. 82/2026, dated 18 November 2026 (CERC website S. No. 577/2026): https://www.cercind.gov.in/2026/orders/246-MP-2026.pdf