Kolkata-based Megatherm Induction Limited, a maker of induction furnaces and transformers, plans to spend ₹70.05 crore to expand its transformer division at Kharagpur in West Bengal. The company set out the two-phase plan in a stock exchange filing on 16 November 2026. It plans to add a second production shed and enter cast resin dry-type transformers, and in a second phase, subject to type tests and approvals, move into 220 kV power transformers. The plan widens a business that already supplies inverter-duty transformers for solar and battery storage projects.
Key Details
The filing splits the project cost into ₹45.05 crore of capital cost and ₹25 crore of working capital. Phase 1 accounts for ₹39.75 crore and Phase 2 for ₹30.30 crore. The land at Kharagpur is owned by the company and is not part of the cost.
The phase-wise capital cost is broken down as follows:
- Shed 2 building, cranes and infrastructure: ₹11.50 crore in Phase 1 and ₹1.00 crore in Phase 2, a total of ₹12.50 crore
- Plant, machinery and utilities: ₹10.05 crore and ₹10.30 crore, a total of ₹20.35 crore
- Testing, certification and approvals: ₹3.20 crore and ₹9.00 crore, a total of ₹12.20 crore
- Working capital: ₹15.00 crore and ₹10.00 crore, a total of ₹25.00 crore
The new building, called Shed 2, is a single pre-engineered structure with a built-up area of 6,300 square metres. It is designed with heavy overhead cranes of up to 63 tonnes and a clear height of up to 12.5 metres. Shed 1, the existing plant, keeps making smaller units of up to 12 MVA and later hosts the cast resin line.
The company has not disclosed a commissioning date for either phase, the funding mix for the project or the annual output it expects from the new lines.
Products and Build Sequence
Phase 1 covers furnace-duty transformers for induction, ladle-refining and arc furnaces, solar and storage inverter-duty transformers, and industrial substation transformers. It also adds cast resin dry-type transformers above 2.5 MVA and up to 5 MVA. Smaller units of typically 2 to 7 MVA, used with the company’s own sintering systems, billet heaters and furnaces, will be made in house once Shed 2 is commissioned.
Phase 2 extends cast resin units to 12 MVA and adds power transformers of 220 kV and above. The company says it will begin type tests and utility approvals for 220 kV early, and commit capital to Phase 2 only after Phase 1 is under way.
The build runs in three steps. Shed 2 is built first, inverter-duty production then moves into it, and the cast resin line is installed in the space this frees in Shed 1. According to the filing, this order lets existing production continue without interruption.
Inverter-Duty Business
Megatherm says every solar inverter block and every battery storage block needs an inverter-duty or multi-winding transformer to step up output to 33 kV. The company holds a 13.2 MVA inverter-duty unit tested by the Central Power Research Institute (CPRI), Bhopal. It also cites approvals from more than ten renewable energy developers and over 400 MVA of orders. Phase 1 includes a CPRI type test of a 20 MVA unit.
Its investor presentation for the first half of the financial year 2026-27 (H1 FY27), filed the same day, says dispatches of inverter-duty transformers for solar and battery energy storage system (BESS) applications have begun. The presentation adds that transformer dispatches started in September and are expected to show in second-half results. It lists Enersure, ReNew and Tata Solar among its clients.
Market Backdrop
The filing cites Central Electricity Authority (CEA) data showing 113,013 MVA of transformation capacity added at 220 kV and above in the financial year 2025-26 (FY26). It also refers to the national transmission plan for 2026-27 to 2035-36, which envisages 827,600 MVA of substations. The filing describes a supply gap, with Ministry of Power lead times of 11 to 15 months for 220 kV units.
For cast resin units, the company points to data centres, wind turbines, metros and airports, where oil-free transformers are preferred inside buildings. It puts the domestic dry-type market at about ₹2,090 crore in 2025, which it derived by converting a third-party estimate of US$246 million at ₹85 to the dollar.
About the Company
Megatherm Induction makes induction melting furnaces, billet heaters, hardening equipment and furnace-related transformers. It also supplies allied steel plant equipment such as ladle-refining furnaces, electric arc furnaces and continuous casting machines. The company reports more than 3,000 installations in over 50 countries, and its plant spreads across 8 acres in Vidyasagar Industrial Park, Kharagpur.
Shesadri Bhusan Chanda is Chairman and Managing Director, and Satadri Chanda is Whole Time Director and Chief Financial Officer. For H1 FY27, the presentation reports total income of ₹196.49 crore, up 20.10% from ₹163.61 crore in H1 FY26.
Recent Pipeline
- August 2026: On 1 August 2026, the company disclosed a joint venture agreement with Smart Induction Converter Technologies S.L. of Spain, according to its later filing.
- September 2026: Dispatch of inverter-duty transformers for solar and BESS applications began, the presentation states.
- October 2026: The joint venture company, Sictech India Private Limited, was incorporated, the company said on 28 October 2026. Megatherm holds 49% and its Spanish partner 51%.
- November 2026: The board approved the H1 FY27 results on 12 November 2026.
- November 2026: The company disclosed the transformer division expansion plan on 16 November 2026.
Outlook
Construction of Shed 2 has started, according to the filing, and the investor presentation says the company is bringing the expansion project forward. Megatherm plans a CPRI type test of a 12 MVA cast resin unit in Phase 2, alongside approvals for its 220 kV range. The company has said transformer dispatches, which began in September, are expected to show in its second-half FY27 results.
Official Sources
- Megatherm Induction Limited – Updates regarding Intended Transformer Division Expansion Projects Initiative (NSE, 16 November 2026): https://nsearchives.nseindia.in/corporate/MEGATHERM_16112026174846_NEAPSANNOUNCEMENTBUSINESSUPDATES16112026.pdf
- Megatherm Induction Limited – Investor Presentation H1 FY27 (NSE, 16 November 2026): https://nsearchives.nseindia.in/corporate/MEGATHERM_16112026121123_NEAPSANNOUNCEMENTINVESTORPRESENTATION16112026.pdf
- Megatherm Induction Limited – Outcome of Board Meeting: Unaudited Financial Results for the Half Year Ended 30 September 2026 (NSE, 12 November 2026): https://nsearchives.nseindia.in/corporate/MEGATHERM_12112026192836_OUTCOMEOFBOARDMEETINGSEPTEMBER2026.pdf
- Megatherm Induction Limited – Incorporation of Joint Venture Company, Sictech India Private Limited (NSE, 28 October 2026): https://nsearchives.nseindia.in/corporate/MEGATHERM_28102026172318_NEAPSANNOUNCEMENTINCORPORATIONOFSICTECH.pdf

Leave a Comment