WBERC Gives In-Principle Clearance to WBSEDCL’s Rs 699 Crore Goaltore Phase II Solar-Plus-Storage Project

The West Bengal Electricity Regulatory Commission (WBERC) has given “in-principle” clearance for the West Bengal State Electricity Distribution Company Limited (WBSEDCL) to spend Rs 699 crore on the Goaltore Phase II solar project in Paschim Medinipur district. The project is a 100 MW (AC) grid-connected, ground-mounted solar photovoltaic plant with a 25 MW / 100 MWh battery energy storage system (BESS). The order, in Case No. OA-566/26-27, is dated 19 November 2026.

What the Commission has cleared

In its order, the Commission accorded in-principle clearance for expenditure of Rs 699.0 crore for the installation and commissioning of the Goaltore Phase II solar plant and its battery storage, under regulation 2.11.1 of the WBERC Terms and Conditions of Tariff Regulations, 2011. The clearance is not a final approval of the project cost. The order states that the final project cost has to be approved separately, and that the Commission may disallow any excess over the approved cost on capitalisation if it finds the justification inadequate.

The Rs 699 crore figure is higher than the Rs 680.78 crore in WBSEDCL’s original petition of 19 May 2026. That estimate excluded land and included GST. In additional information filed on 1 September 2026, WBSEDCL submitted a revised tariff computation that included interest during construction, putting the project cost at Rs 699 crore. The Commission’s order clears that amount.

Project scope and timeline

The solar plant is rated at 100 MW (AC) and 120 MW (DC). WBSEDCL told the Commission that it will be built as a turnkey engineering, procurement and construction (EPC) contract with 12 years of comprehensive operation and maintenance, along with an implementation supervision contract for consulting services. The battery system is 25 MW / 100 MWh and will be charged wholly from the co-located solar plant.

About 950.16 acres at Keshia, Pirmasholi and Nischintapur villages has been identified for the project. The Commission noted that it is an extension of the existing solar park on vacant land within the same plot and needs no fresh land acquisition. Power will be evacuated from a 33 kV/132 kV pooling substation through an approximately 30.43 km, 132 kV line to the Chandrakona Road grid substation, with the line works to be carried out by the West Bengal State Electricity Transmission Company Limited (WBSETCL) or another authorised agency. The whole project is targeted for completion by October 2027.

Advertisement

Phase I at Goaltore is an existing 112.5 MW (AC) solar project developed by WBSEDCL. WBSEDCL’s board gave administrative approval for Phase II on 12 February 2026.

Cost break-up and financing

The Commission’s order reproduces WBSEDCL’s cost table. The PV system for 120 MW (DC) / 100 MW (AC) is priced at Rs 432.33 crore including GST, with Rs 50 crore for operations and maintenance. The BESS is priced at Rs 104 crore excluding GST, with Rs 18.72 crore of GST and Rs 5 crore for operations and maintenance. Consulting and other costs, evacuation upgrades and contingencies make up the rest of the Rs 680.78 crore in the petition.

The project is financed with external aid from Kreditanstalt für Wiederaufbau (KfW) of Germany. The Department of Power of the West Bengal government approved the project on 7 May 2025, and the loan and grant agreements with KfW were signed on 15 December 2025. The estimated cost of about EUR 75.5 million is to be financed in a 70:30 debt-equity ratio. The order records a concessional KfW loan of up to EUR 48.12 million and a grant of up to EUR 5 million for the battery component, and about Rs 188 crore of equity from the Government of West Bengal. The loan runs up to 15 years including a five-year grace period, at a fixed 3.00% a year.

Expected generation and the Commission’s directions

WBSEDCL expects the solar plant to generate about 161.40 million units (MU) a year and the battery about 21.10 MU a year, with a design life of 25 years for the solar plant and 12 years for the batteries. In its revised computation, it assumed a capacity utilisation factor of 20.78% and design energy generation of 182 MU a year. The Commission directed WBSEDCL to establish the CUF and projected generation on the basis of actual site data when tariff is determined.

Advertisement

The energy will be used by WBSEDCL to meet its renewable purchase obligation (RPO). The order also lists several directions: WBSEDCL must award works through transparent competitive bidding under the procurement guidelines for the externally aided component and pass on the benefit of the discovered price to consumers; it must take the Commission’s approval before capitalising assets if costs escalate; it must submit a detailed computation of interest during construction; and the benefit of the KfW grant must be reduced in full from the capital cost. The Commission received no suggestions or objections on the petition by the 29 September deadline.

What it means for West Bengal’s clean-energy sector

The clearance is a regulatory step that lets WBSEDCL proceed to tendering, with the Commission retaining the right to scrutinise the final cost. For West Bengal, the project pairs utility-scale solar with storage at an existing solar park, using land and a substation location that already support Phase I. The order says the battery will improve grid stability and offer peak support, and it ties the project to the state’s RPO compliance and to participation in the National Solar and Storage Mission.

Official references

1. West Bengal Electricity Regulatory Commission, Order in Case No. OA-566/26-27, “In-principle Clearance” for 100 MW (AC) Solar PV power plant with 25 MW / 100 MWh BESS at Goaltore (Phase II), Paschim Medinipur, WBSEDCL, dated 19 November 2026: https://wberc.gov.in/sites/default/files/Final%20order-%20OA-566.pdf

2. WBERC website, news and orders listing: https://www.wberc.gov.in/index.php