POWERGRID Declared Successful Bidder for 3×500 MVA Humnabad Substation in Karnataka Under TBCB; Quoted Annual Charges Rs 243.34 Crore

Power Grid Corporation of India Limited (POWERGRID) has been declared the successful bidder under Tariff Based Competitive Bidding (TBCB) for the POWERGRID Humnabad substation project in Bidar district, Karnataka. The company quoted annual transmission charges of Rs 243.34 crore for the project, which is an intra-State transmission system. POWERGRID told the stock exchanges on 11 November 2026 that it received the Letter of Intent (LoI), dated 10 November 2026, on 11 November 2026.

What the POWERGRID filing says

The disclosure was made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The project is named “Establishment of 3X500MVA 400/220kV sub-station at Humnabad in Bidar District and associated transmission lines”. It will be built on a Build, Own, Operate and Transfer (BOOT) basis.

The main points are:

  • Bidder: Power Grid Corporation of India Limited.
  • Quoted annual transmission charges: Rs 243.34 crore.
  • Letter of Intent: dated 10 November 2026, received on 11 November 2026.
  • Mode: TBCB, on a BOOT basis.
  • Location: Humnabad, Bidar district, Karnataka.

The filing describes the scope in two parts. The first is a new 400/220 kV substation at Humnabad in Bidar district, with a capacity of 3×500 MVA. The second is the construction of 400 kV and 220 kV transmission lines passing through Karnataka, together with the associated bays.

The filing does not give the name of the special purpose vehicle, the commissioning timeline, the length of the lines or the project cost. These points were not disclosed, so this report does not state them.

Advertisement

POWERGRID’s tally of TBCB wins in FY 2026-27

POWERGRID says that with this project it has secured eleven transmission system projects under TBCB in FY 2026-27 so far. The cumulative annual transmission charges of these eleven projects stand at Rs 8,106.97 crore. On these figures, the Humnabad project accounts for about 3% of the cumulative annual charges, a simple share calculated by VYQON from the two numbers in the filing.

The wins show the company’s growing activity in competitive transmission bidding, where developers compete on the annual charge they quote. Under TBCB, the bidder that quotes the lowest annual transmission charges for the specified scope of work wins the project.

The bidding process for the Humnabad scheme

The Humnabad scheme was put out for bids by PFC Consulting, the bid process coordinator, in early 2026. The tender called for a 3×500 MVA, 400/220 kV substation at Humnabad together with associated transmission lines, and the last date for submitting bids was 14 April 2026.

Reports on the tender describe the scope of the transmission lines in more detail. It includes a loop-in loop-out (LILO) of the 400 kV double-circuit line between YTPS and Kalaburagi, 220 kV double-circuit lines to the Ganagapura and Santhapur substations, and a LILO of existing 220 kV lines from Sedam and Kapnoor. The tender documents provide that Karnataka Power Transmission Corporation Limited will make the land available for the project.

POWERGRID’s filing confirms the substation and the 400 kV and 220 kV lines, but it does not list these line-level details. They come from the tender coverage and should be read as the scope of the bid, not as the final contract terms.

Advertisement

Why it matters for Karnataka’s grid

Coverage of the tender describes the transmission system as part of a plan to evacuate renewable power from north Karnataka to load centres in the south of the State. A 400/220 kV substation with 1,500 MVA of transformation capacity (three units of 500 MVA) gives the State grid a new point to step power between the 400 kV and 220 kV networks. The lines that are looped into this substation connect it to existing 400 kV and 220 kV corridors in the region.

The project is intra-State, so it forms part of the State’s own transmission plan and not the inter-State system. Karnataka’s regulator has notified final regulations for transmission licences under TBCB, which shows that competitive bidding is now the route for new State-level transmission. For readers who want to follow the sector, VYQON has covered the KERC TBCB regulations and POWERGRID’s capex guidance for FY27.

What it means for India’s clean-energy sector

Transmission is a bottleneck for renewable power in India, because solar and wind plants are often built far from the cities that use the electricity. New substations and lines in renewable-rich regions help move this power to demand centres and reduce the risk of curtailment. Competitive bidding helps keep the cost of such assets visible, since each project’s annual charge is set in an open bid.

For POWERGRID, the win adds one more project to its TBCB portfolio for the year. The Rs 243.34 crore figure is the annual charge the company quoted, not a capital cost, and the project cost has not been disclosed.

Official references

  1. POWERGRID, Regulation 30 disclosure to NSE and BSE dated 11 November 2026, “POWERGRID declared as successful bidder under TBCB”: https://www.bseindia.com/xml-data/corpfiling/AttachLive/787573c9-12cc-44d9-84ea-cebbfc9b630c.pdf