In a significant regulatory intervention, the Ministry of New and Renewable Energy (MNRE) deactivated 66 registered vendors on August 26, 2026, following a data-driven investigation into excessive application backlogs under the PM Surya Ghar: Muft Bijli Yojana. The ministry’s analysis exposed a pattern of “artificial hoarding” where vendors accepted consumer applications far exceeding their demonstrated installation capacity, threatening the scheme’s time-bound execution. This administrative action aims to protect consumer choice and ensure the timely disbursement of central financial assistance as the program enters its final phase.
Details of the Administrative Action
The MNRE has implemented immediate restrictions on the 66 identified vendors to halt the further accumulation of unserviceable backlogs. Effective immediately, these underperforming entities are subject to the following regulatory constraints:
- Prohibition of New Business: Vendors are barred from accepting any new consumer applications through the national portal.
- Removal from Selection Portal: The affected vendors no longer appear on the consumer vendor-selection page, preventing new users from inadvertently entering backlogged pipelines.
- Restricted Portal Access: While new registrations are blocked, the vendors maintain functional portal access exclusively for completing installations and processing documentation for existing applications.
These measures ensure that consumers already under contract are not abandoned, while preventing the vendors from “trapping” additional households in delayed installation cycles.
Performance Benchmarks and Analysis Criteria
The deactivation follows a comprehensive audit of portal data during the performance period of April–June 2026. The MNRE focused on the “Agreement Uploaded” metric to identify vendors whose projected completion times for current backlogs exceeded reasonable scheme horizons. The investigation exposed that several vendors were operating with volumes of applications that their demonstrated installation history proved they could not execute within the remaining lifecycle of the scheme.
MNRE Performance Benchmarks (April–June 2026)
| Criteria | Regulatory Impact |
| Pending “Agreement Uploaded” applications exceeding demonstrated operational capacity | Immediate one-month deactivation and removal from the portal’s vendor-selection page |
| Identification of “artificial hoarding” of consumer applications | Heightened risk to central subsidy disbursement and potential forfeiture of Performance Bank Guarantees (PBG) |
The One-Month Remedial Window and Conditions
The ministry has provided a 30-day remedial window, beginning from the date of notification, for the 66 vendors to demonstrate improved performance. Reactivation is not guaranteed and is strictly contingent upon the vendors bringing their delivery pendency within acceptable scheme timelines.
During this review period, vendors must accelerate the clearance of their existing backlogs. Those that fail to significantly improve their execution metrics or demonstrate a clear alignment with installation capacity will face a further extension of their deactivation status. Continued non-compliance may lead to more severe enforcement actions, including the permanent loss of empanelment and the forfeiture of the Performance Bank Guarantee (PBG) previously submitted to the Distribution Companies (DISCOMs).
Operational Directives for All Registered Vendors
Beyond the specific deactivations, the MNRE has issued broader operational directives to all registered participants in the PM Surya Ghar ecosystem. The ministry’s guidelines emphasize the following compliance standards:
- 60-Day Retention Limit: Vendors are advised to clear or process consumer applications within a maximum of 60 days. Retaining applications beyond this period without valid, documented reasons is now flagged as a performance violation.
- Capacity Alignment: All vendors must align their application intake with their actual, verifiable execution and installation capacity.
- Data Integrity: Vendors are required to ensure that all data uploaded to the national portal, including equipment serial numbers and installation dates, remains accurate and verifiable to avoid automated deactivation triggers.
Current Scheme Context
This regulatory crackdown occurs as less than nine months remain before the scheduled conclusion of the PM Surya Ghar: Muft Bijli Yojana. By deactivating underperforming vendors, the MNRE is moving to protect consumer interests and ensure that rooftop solar installations are completed in a time-bound manner, securing the disbursement of central financial assistance. The ministry has confirmed its commitment to ongoing portal monitoring, signaling that data-driven enforcement will remain the primary tool for ensuring performance compliance throughout the remainder of the scheme.
Official Government Sources & Reference Links
- PM Surya Ghar: Muft Bijli Yojana National Portal The official national portal for registering consumer applications, verifying DISCOM-empanelled solar vendors, checking ALMM compliance, tracking application progress, and filing initial grievances.
- Ministry of New and Renewable Energy (MNRE) The central ministry portal providing official scheme directives, ALMM (Approved List of Models and Manufacturers) List-I updates, technical guidelines, and policy notifications.
- CPGRAMS — Centralized Public Grievance Redress and Monitoring System The central government portal for escalating unresolved vendor non-compliance or scheme disputes directly to the MNRE or DISCOMs.
- National Consumer Helpline The official portal for filing consumer protection complaints regarding deficient service, vendor default, or contract violations.
- National Cyber Crime Reporting Portal The government portal for reporting unauthorized financial demands, digital payment fraud, or middleman scams.
- Gujarat Energy Development Agency (GEDA) An official State Nodal Agency (SNA) portal for handling state-level escalations and subsidy process transfers when installers default.
Official Policy Directives & Notifications Cited
- MNRE Office Memorandum (22 June 2026): Standard Operating Procedure (SOP) to Address Vendor Violations Under PM Surya Ghar Scheme — Establishes mandatory technical standards, automated grievance triggers (Case-A, Case-B, Case-C), and progressive portal deactivation protocols.
- MNRE Official Notification (26 August 2026): Deactivation Notice for 66 Underperforming PM Surya Ghar Vendors — Mandates a 30-day portal deactivation for vendors accumulating excessive pending applications beyond their operational capacity.