ReNew and Purvah Green Win NPCL’s 300 MW RTC Renewable Auction at ₹4.43-4.44/kWh

Noida Power Company Limited (NPCL) has concluded its auction for 300 MW of firm and dispatchable round-the-clock (RTC) renewable power with energy storage. In the NPCL 300 MW RTC auction, whose result was reported on 24 November 2026, ReNew Private Limited won 85 MW at ₹4.43 per kWh, the lowest tariff, and Purvah Green Power Pvt Ltd won 215 MW at ₹4.44 per kWh. The weighted average tariff for the full 300 MW is ₹4.44 per kWh. The power will be supplied under a 25-year power purchase agreement (PPA), with supply expected to begin from FY 2028-29.

NPCL 300 MW RTC auction: bids and tariffs

Seven developers took part and together bid for 695 MW, which is about 2.3 times the capacity on offer. The gap between the two winning tariffs is just ₹0.01 per kWh. ReNew’s lowest tariff of ₹4.43 per kWh is 15.78% below the start price of the auction.

The electricity will come from renewable energy projects connected to the Inter-State Transmission System (ISTS), located anywhere in India.

Supply conditions in the tender

The tender sets strict performance conditions for the winning developers:

  • Availability of at least 90% in every 15-minute block.
  • Specified minimum supply during six peak hours of the day.
  • An annual capacity utilisation factor (CUF) of at least 75%, with a permitted variation of plus or minus 10% over the contract period.
  • Liquidated damages for any shortfall in energy, set at 1.5 times the tariff.
  • A tariff that stays fixed for the full 25 years.
  • The storage must be charged from renewable energy supply within 24 months.

What the UPERC order approved

The auction followed an order of the Uttar Pradesh Electricity Regulatory Commission (UPERC), dated 27 October 2026, in Petition No. 2418 of 2026. NPCL had approached the Commission under Section 86(1)(b) and (e) of the Electricity Act, 2003 for approval of long-term procurement of 300 MW of RE-RTC power through tariff-based competitive bidding. The petition also sought approval of a deviation from the Guidelines for Tariff Based Competitive Bidding Process for Procurement of Firm and Dispatchable Power from Grid Connected Renewable Energy Power Projects with Energy Storage Systems, dated 9 June 2023.

Advertisement

The Commission said that the procurement is in line with the requirement for long-term firm capacity that it had directed in its order dated 24 June 2026 in Petition No. 2309/2025, and that it is necessary for NPCL to meet its anticipated power requirement in a reliable and economically prudent way. It approved the procurement of 300 MW of firm and dispatchable RE-RTC power on a long-term basis.

The Commission also approved the tender documents with certain clause changes. These include the deviation sought by NPCL to allow the entire 300 MW to go to a single successful bidder. The order clarified that NPCL must ensure this happens at the lowest (L1) tariff only; otherwise, bucket filling is to be done within a tariff range of L1 plus 2%. It also approved NPCL’s amendment that only bidders holding a final grant of connectivity from the Central or State Transmission Utility at the time of bid submission can participate, provided the start date of connectivity in the final grant is on or before 31 December 2028.

Among other directions, the Commission asked NPCL to constitute a Commissioning Committee, with one external member, to verify the declared rated capacity of the renewable and storage components before supply begins.

Why NPCL needs the power

NPCL supplies electricity in Greater Noida. According to the Commission’s order, NPCL recorded a power drawal of 4,327 million units (MU) in FY 2025-26, an increase of 8.1% over FY 2024-25. The Central Electricity Authority’s long-term forecast of March 2024 for the licensed area projects energy requirement rising from 4,647 MU in FY 2025-26 to 8,684 MU in FY 2031-32. Peak demand is projected to rise from 864 MW to 1,663 MW over the same period. For FY 2028-29, when the new supply is expected to begin, the forecast is 6,508 MU of energy and 1,228 MW of peak demand.

Advertisement

The order also lists NPCL’s existing long-term tie-ups for supply from FY 2028-29 onwards. These include 100 MW of firm and dispatchable renewable energy (FDRE) power from SJVN, giving about 70 MW of RTC at the NPCL bus, and a 300 MW wind-solar hybrid project from Deshraj Solar Energy Power Limited, expected to give about 136 MW of RTC power. The new 300 MW adds a large block of round-the-clock renewable supply to this mix.

What it means for India’s clean-energy sector

The result adds to a growing list of RTC and FDRE auctions in India, where distribution companies now buy renewable power that is available through the day and evening rather than only at solar hours. A tariff of ₹4.43-4.44 per kWh for 25 years, flat, shows how developers price solar and wind combined with storage when supply is firm and penalties are tied to availability. The 2.3 times oversubscription shows strong developer interest in a 300 MW tender.

For storage suppliers and engineering, procurement and construction (EPC) firms, the 24-month window to charge the storage from renewable power and the connectivity cut-off of 31 December 2028 will shape project schedules.

Purvah Green Power has also featured in our earlier report on its pending acquisition of a 1.4 GW solar portfolio from ReNew.

Official references

  1. Uttar Pradesh Electricity Regulatory Commission, Order dated 27 October 2026 in Petition No. 2418 of 2026 (Noida Power Company Limited, 300 MW RE-RTC procurement): https://www.uperc.org/App_File/Pt-no-2418of2026NPCL-27-10-2026-pdf1028202641617PM.pdf
  2. UPERC, Orders page: https://www.uperc.org/Order_Users.aspx